Beck Engineering reported that 2nd Ave South construction is moving forward, 16th Street is open both directions, the water main has been installed, storm sewer work continues and the contractor has 11 working days remaining; council requested ADA sidewalk checks and attention to a hump near 16th Street.

The full story

Jason Eygabraod of Beck Engineering told the council that the 2nd Ave South project is progressing and that 16th Street has been reopened to both north‑ and southbound traffic. The water main is installed and the contractor is working on the storm sewer. He said there are 11 working days remaining on the project.