Forsyth Tech asks county to consolidate bond proceeds to finish Learning Commons project
Sep 15, 2026
Sep 15, 2026
Forsyth Tech requested moving remaining 2016 bond proceeds into the Learning Commons to cover inflation‑driven cost increases; staff said consolidation would add $5,319,331 and make the project's bond‑proceeds budget $22,519,900, with total project costs (including SCIF and other sources) shown in packet at about $35.0 million.
The full story
Forsyth Tech staff asked the Forsyth County Board to approve consolidating remaining 2016 bond proceeds from completed projects into the college’s Learning Commons project so construction can move forward.