Board hears timeline, amounts and bondholder representative for Regional Center refinancing

Sep 14, 2026

Board members received details that the anticipated USDA payoff is about $8.5 million, the resolution sets a maximum draw parameter of $10 million, construction is estimated at roughly two years with a draw toward summer 2028, and Hamlin Capital Management was named as bondholder representative.

The full story

Board members asked when any refunding draw would occur and who would bear risk. Bond counsel said the financing is a drawdown structure: Regional Center will requisition amounts as needed and the draw for refunding is anticipated toward the end of a roughly two‑year construction period—about summer 2028—though counsel allowed it could occur sooner if required by USDA timing.