Bond projects progressing; district unveils public bond budget and oversight tools

Aug 18, 2026

Bond project manager Ken Wolf reported Midway High additions are on schedule for a July completion next year and currently tracking under budget; communications director Emily Parks showed a public bond webpage with an interactive budget workbook and quarterly oversight meetings.

The full story

Board members heard that construction for the Midway High School renovations is underway, with the building pad complete and pier drilling in progress. Ken Wolf said foundations and underground utility relocations are complete and subcontractor submittals are under review; the project is scheduled for completion by the end of July next year.