Master plan remodel: $710,000 in change orders and early‑to‑mid January completion target
Summary
Staff reported roughly $710,000 in change orders through phases 1 and 2 and committed spending just under $7.4M; about $620,000 in CIP commitments were folded into the project leaving roughly $200,000 contingency and an overall completion target of early‑to‑mid January, with demo/abatement for phase 3 expected to finish by early October.
The committee heard a separate master plan remodeling budget and schedule update. A staff presenter said the project has added roughly 57 change orders across phases 1 and 2, with total change‑order value around $710,000; committed project spend (actuals, encumbrances and purchase orders) is just shy of $7.4 million. "Committed total thus far in the project, we are just shy of 7,400,000 in spend," the presenter said, and noted about $620,000 in additional CIP commitments were included, leaving an anticipated remaining contingency of roughly $200,000.
On schedule, the presenter reported that several county offices had reopened on the first floor and that phase 3 abatement/demolition was underway, with abatement/demo areas expected to be fully complete near early October and overall project completion (including moves of natural resources and community development) tracking toward early to mid‑January.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.