County IT contractor urges prompt RFP for server hardware; lead time about three months

Sep 8, 2026

Applied Connective recommended issuing an RFP for server hardware promptly because lead time for new servers is approximately three months; the Board asked the County Clerk to prepare and distribute the hardware RFP while Applied Connective would handle installation and migration.

The full story

Applied Connective representative Matt Childress presented a preliminary RFP for the county's server replacement project, telling the Board the prior proposal totaled roughly $33,000 with about $23,000 attributable to hardware. Childress said current lead time for a new server is approximately three months and recommended the county move forward with an RFP for hardware while retaining Applied Connective for installation and migration.