Dwight School Building Committee · September 9, 2026

Tekton and Collier presented an updated cost reconciliation and value-management plan for the Dwight School project, reporting roughly $9.1 million in savings from plan changes and proposing a reduction in design contingency from 7.5% to 5% to bring the project closer to budget; the committee discussed HVAC options (VRF, chilled beam, geothermal), PV and rebate timing, ICF construction trade-offs, next steps and upcoming board presentations.