Council approves sidewalk, parking and pavilion change order for City Park skate-park phase
Loading...
Summary
The council approved a change order adding four parking stalls, sidewalk repairs, and a 20-by-20 pavilion pad to City Park phase 2; the skate park itself is about 95% complete and the whole project roughly 75% complete.
The City Council approved a change order for Phase 2 of the City Park upgrades that adds four parking spaces, repairs to uneven sidewalks around the skate park and a 20-by-20 pavilion pad to be relocated near the skate park.
Staff reported the skate-park feature is about 95% complete and the overall park project about 75% complete; site work including drainage, seating and paving remains. The contractor is expected to finish in roughly 6 to 8 weeks, and staff said the change order items will be among the contractor’s final tasks.
Council discussed pavilion placement and confirmed the slab will be installed near the skate-park area; public-works staff also said they will remove the perimeter fence when the contractor is ready, and they are monitoring unauthorized public access to curing concrete.
Council approved the change order and asked staff to continue coordinating completion activities and notify the council as the contractor finalizes site work.