Board of County Commissioners Meeting - November 10, 2026
The Washington County Board of County Commissioners heard staff updates and approved several budget adjustments and contract awards. Commissioners also discussed the county’s data center moratorium, technology costs and a state highway safety plan.
Discussion Points
•Officials discussed a reserve level of about 43 days against a 45-day goal and compared the school board’s target with GFOA best practices.
•The county has not approved a data center, and staff are considering possible local regulation changes.
•The county moratorium applies to unincorporated areas; incorporated municipalities have separate zoning authority under the law described by Gordon.
•The year-end fund balance was $5.4 million, about $1.4 million above the final anticipated budget.
Decisions
•Commissioners approved the fiscal 2026 year-end budget adjustment.
•The surplus remained in the unassigned fund balance; no different use was approved.
Directions
•The Planning Department was preparing a frequently asked questions webpage.
Board of County Commissioners Evening Meeting with the Town of Smithsburg 11/10/2026
Washington County commissioners and Smithsburg representatives discussed sewer upgrades, pedestrian safety, Smithsburg’s water-system options, wastewater treatment capacity and development. The water-system discussion included competing views about costs, infrastructure needs and whether to explore alternatives to a potential transfer to Hagerstown.
Discussion Points
•Participants disputed how a county arrangement might compare with Hagerstown on cost, speed and long-term infrastructure responsibility.
•Smithsburg was pursuing preliminary discussions with Hagerstown about a possible water-system transfer.
•The county representative reported that plant upgrades were complete and capacity was available, with minor commissioning tasks remaining.
•The county said it was studying wells near Smithsburg and had taken samples.
•The mayor said property and income tax revenue were flat and described restricted funds and grants as sources of revenue growth.
•The town described aging pump stations and funding sources for the replacement project.
•The town described planned route, crossing and accessibility improvements, along with engineering work underway.
•The town discussed the status of Cloverly and Garden Hour States and the potential relationship between development and local revenue.
•Town representatives cited roughly $10.5 million in identified water-system improvements.
Decisions
•A motion to adjourn passed 4-0.
Directions
•Mayor Souder said he would take the county-option question back to the Smithsburg council.
•The town council had advanced an RFP for a special taxing district financial adviser.
Board of County Commissioners Meeting - October 13, 2026
Washington County Board of County Commissioners met Oct. 13, 2026; commissioners approved multiple contracts and grants, heard an annual tourism report, received requests from community groups and clarified that the county did not approve a federal purchase of a warehouse in Williamsport.
Discussion Points
•Coalition reported $42M in returns and outlined project-specific asks.
•Commissioners asked membership and value questions; CVB answered on dues and retention.
•Commissioners debated appropriate county contribution and the relative share of partner organizations.
•County denies involvement in federal acquisition of Wright Road warehouse and warns that false information is circulating online.
•CVB reported visitor and lodging statistics, grant revenues, and details of advertising campaigns.
•IT explained choice to move from thin clients to desktops due to server obsolescence and subscription costs.
•Medical and advocacy professionals presented statistics and the importance of coordinated responses to intimate-partner violence.
•Red Cross outlined a smoke‑alarm installation program and volunteer roles.
•Scope and cost were questioned on several awards; BZA legal services scope confined to hearings and written decisions (not appellate litigation).
•Staff presented a multi-month timeline for the data center moratorium review and noted the moratorium covers only unincorporated areas; municipalities retain zoning authority.
Decisions
•Awards approved as submitted.
•Board approved county support for coalition advocacy ($10,000)
Directions
•County to coordinate with coalition and delegation; commissioners encouraged to meet with governor and delegates early.
•Departments to proceed with contract execution and provide follow-up reports as scheduled.
•Planning Commission to hold workshops Oct. 26–Nov. 26 and continue discussions in Jan. 2027; staff to draft proposed local zoning amendment March 2027; Board public hearing anticipated Apr–Jun 2027.
•Public urged to sign up for Red Cross 'Sound the Alarm' installations; county budget already includes Character Counts funding increase from prior year.
•Staff to continue to support CVB grant applications and share metrics with the Board as requested.
Board of County Commissioners Meeting - September 29, 2026
Washington County Board of County Commissioners meeting covering grants, procurement, airport site development, personnel actions and clarifications about a federal warehouse purchase and data-center moratorium. Multiple funding awards and procurement decisions were approved by voice vote.
Discussion Points
•Clarified county noninvolvement in a federal warehouse purchase.
•Clarified eligible geography (countywide), and that funds are not cannabis proceeds restricted.
•Confirmation that product aligns with existing county Rubrik implementation.
•Current units date from 2019 and have an expected 8‑year lifespan.
•Details of SAFER grant funding shares and estimated county fiscal impacts.
•Device costs (~$65,000 with trade‑in to ~$60,000) and replacement schedule for 15 devices.
•Explained performance metrics and abatement plan alignment.
•Match mechanics: 3:1 requirement and use of previously committed terminal investments as match.
•Motion and vote to enter a closed session.
•Number of bids received (10) and procurement rationale for lowest responsive bidder.
•Panel interview process and salary grade/step for hires.
•Proposed timeline for planning commission workshops and drafting local regulations.
•Reappointment term dates for airport advisory commission.
•Recruitment timing and possible lateral‑transfer bonuses to expedite staffing.
•Site location (northwest quadrant of airport), removal of tailings and grading strategy.
•Staff recommendations for data‑center zoning and technical requirements (energy plans, noise limits, setbacks).
Decisions
•Board approved moving forward to accept SAFER grant (acknowledged by directors)
•Board approved the award by voice vote.
•Board authorized application and acceptance of potential award.
•Board authorized submission and acceptance of possible award.
•Board voted to approve the grant awards by voice vote.
•Hires and reappointments approved; board entered closed session.
Directions
•County Clerk to record reappointments and update commission roster.
•Execute grant agreements and disburse funds consistent with program requirements.
•HR to process hires and onboarding paperwork.
•If awarded, plan and schedule grading and site remediation activities.
•Procurement to finalize contract and proceed with implementation.
•Staff and HR to explore incentives and present them for consideration before public hiring announcements.
•Staff to provide proposed regulation summary and recommendations to the planning commission for workshops Oct.–Nov. 2026 and to draft local zoning amendments for March 2027 review.
•Staff to submit application and, if awarded, use operating funds for required match.
•Staff to submit application and proceed with matching documentation with MEDCO.
Washington County officials and community partners sealed a 250th‑anniversary time capsule at City Park on 09/06/2026 to be opened on 09/06/2076 during the county's 300th anniversary; items represent local governments, schools, businesses and emergency services.
Discussion Points
•Items contributed by municipalities, schools, county departments and community partners
•List of artifacts contributed by municipalities, schools and county departments
•Osborne family assisted with logistics
•Planned opening date of 09/06/2076
•Purpose of the capsule as a historical snapshot
•Richard Ward (Richards Wilbert) donated vault to protect time capsule
Decisions
•Capsule sealed and placed in donated vault; no further administrative action recorded
Board of County Commissioners Meeting - September 22, 2026
County commissioners held a regular meeting addressing personnel reclassification, an airport hangar lease extension, new parks concussion and abuse-prevention policies, and staff updates clarifying a federal property purchase and an existing data center moratorium for unincorporated Washington County.
Discussion Points
•Commissioners asked about signing, distribution, and orientation procedures.
•Commissioners asked about the hangars' age and approved the extension to allow additional negotiation time.
•Gordon corrected misinformation about a Federal warehouse purchase and clarified county jurisdiction.
•Sheriff's Office explained the reclassification fills a supervisory void from previous reclassifications.
•Staff clarified that existing procedures and training were in place; the policy consolidates them and specifies reporting paths.
•Staff explained a temporary uniform rental rate of $7/sq ft and an estimated revenue increase of about $81,374.20.
•Staff outlined potential data center ordinance changes and a planning commission schedule through March 2027.
•Staff recapped MDOT priorities including I-81 phases, interchange improvements, airport needs, and pedestrian safety.
•The position affected is number 231 and an existing employee is in the role awaiting approval.
•Travelers Insurance recommended adoption of a formal policy to mitigate liability and standardize response.
•Travelers Insurance recommended a formal policy for abuse and misconduct prevention; staff summarized document contents and distribution methods.
Decisions
•12-month temporary lease extension approved 5-0.
•No Board approval occurred for the federal purchase; the Board maintains a moratorium on data centers in unincorporated areas.
•Policy adopted 5-0.
•Policy adopted by voice vote.
•Reclassification approved 5-0.
Directions
•Distribute policy and ensure program coordinators have incident contact numbers.
•HR and Risk Management to distribute policy and document orientation events.
•HR to implement reclassification and update payroll after Board approval.
•No new positions to be created; staff will use existing contacts.
•Planning commission to hold workshops Oct–Nov; continue discussion Dec–Jan; produce draft zoning amendment by March 2027.
•Public Works/Airport to continue negotiations and return with a proposed multi-year lease when ready.
Board of County Commissioners Meeting - September 15, 2026
Washington County Board of County Commissioners met on 2026-09-15. The board approved minutes, enacted multiple grant applications and procurement awards, heard a policy briefing from the Maryland Association of Counties, presented proclamations including recognition for Georgine Charles, and discussed infrastructure projects including a landfill pretreatment facility and Cascade Town Center grant application.
Discussion Points
•Design choices (bridge crossing vs. under‑creek) affect feasibility and cost.
•Estimated capital cost ($11–$12M) and projected annual savings (~$1M).
•Funding through future bond issuance and landfill fees.
•Gordon clarified the county had no role in a separate federal warehouse purchase in Williamsport.
•Gordon corrected misinformation that the county approved a data center and clarified the moratorium applies only to unincorporated areas.
•Scale of the event (volunteer numbers, luminaries placed) and community/visitor impact.
•State revenue shortfalls, housing unit shortfalls, electricity affordability and potential county impacts.
•Whether the county should act as applicant/grantee instead of the developer (staff said county has done this before).
•Which portions of the requested funds are strictly infrastructure vs. building improvements.
•Who bears financial liability if the project fails (subrecipient agreement terms and legal review will determine).
Decisions
•Approved $150,000 design budget transfer.
•Board approved applying for $1,250,000 contingent on legal review.
Directions
•Proceed with application and prepare subrecipient agreement for legal review.
•Proceed with design and return with construction cost estimates.
Board of County Commissioners Meeting - August 25, 2026
Washington County Board of County Commissioners held a regular meeting on Aug. 25, 2026, covering routine approvals, county updates (including a data center moratorium and clarification about a federal warehouse purchase), a public hearing to add nonprofits to the county's 1-108 funding list (nine organizations were approved), multiple procurement and grant approvals, and land preservation and park infrastructure actions.
Discussion Points
•Applicants presented program missions and budgets; citizens offered both support and opposition during public comment.
•Commissioners asked about number of bidders and cost reasonableness; staff said value compared favorably to steel alternatives.
•Emergency services explained the need for maintenance and the 5-year pricing lock.
•Leases structured as dollar-buyback for capital accounting; interest rate cited at 4.99%.
•Other residents highlighted the role of nonprofits in supporting children whose caregivers have been detained or deported.
•Public works explained FRP advantages and that limited suppliers exist for this span and load.
•Sheriff discussed lab turnaround time and interjurisdictional access.
•Speaker Sean Porter criticized nonprofit funding and taxes using profane language.
•Staff clarified the county had not authorized or participated in the federal warehouse site selection for Williamsport.
•Staff described volunteer committee review, financial checks and site visits.
•Staff explained enterprise fund constraints and trade-ins; commissioners questioned leasing vs. purchase.
•Staff explained that state law preempts local zoning for recovery residences and that updated state licensing will require recovery houses to be licensed beginning Oct. 1.
•Staff reiterated that the data-center moratorium applies only to unincorporated county areas and that municipalities retain planning/zoning authority for annexed areas.
Decisions
•Board approved sole-source analyzer purchase and ventilator maintenance agreement.
•Contract awarded to Creative Pultrusions (low bid $51,190).
•Motions to approve lease-purchases passed by voice vote.
•Nine organizations added to the 1-108 list by board vote (5–0).
•No immediate regulatory changes adopted; matter to be continued for staff review.
•Public comment concluded; board proceeded to deliberation and vote on 1-108 list additions.
Directions
•Coordinate with municipal partners to expand lab capacity.
•Grant office to publish the updated list and advise organizations of application procedures.
•No funding awarded at this meeting; organizations must apply through the committee process.
•Proceed with lease documents and finalize trade-in arrangements.
•Proceed with procurement and coordinate installation schedule with trail construction.
•Proceed with procurement and schedule maintenance.
•Staff to continue research and return with best-practice recommendations and potential zoning/policy changes on data centers.
•Staff to monitor state licensing implementation for recovery residences and coordinate with county delegation as needed.
Board of County Commissioners Meeting - August 11, 2026
Washington County Board of County Commissioners meeting covering commissioner reports, RISE zone support for Hagerstown Community College, Gaming Commission grant awards, multiple contract awards and transfers, grant approvals, and a mutual aid MOU; board voted unanimously on listed motions and recessed to closed session.
Discussion Points
•Application process and public presentations were held; 58 of 89 eligible applications funded.
•County administrator explained Maryland statute preempting local zoning over small and large halfway houses.
•County plans to include similar legislation in the 2027 General Assembly.
•Facility will support high-school teams and community programs.
•FY26 funds available ($2,367,846.22) and increase from prior year.
•Grant amount requested: $648,171 (as awarded).
•Grant reimburses personnel costs and certain fringe benefits under Title IV-D.
•Hagerstown Community College agreed to act as anchor institution.
•LaserFISH renewal will streamline paper processes and is part of current workflows.
•Little League grants require county beneficiary status because facilities are on county property and will fund ADA restrooms and storage improvements.
•MOU highlights: assistance contingent on staffing, waiver of claims except for gross negligence, billing for services, and cross-training encouragement.
•RISE offers biotech credits, fee waivers, and priority access to a Build Our Futures grant.
•Security upgrades replace end-of-life hardware and add modern encryption support.
•Staff detailed site prep and erosion control reduced costs.
•Tennis resurfacing uses cooperative contract and CIP funding; procurement presented scope and system to be used.
•Transfer covers wellhouses and lines not transferred when the base closed; county will use wells to meet water demand.
Decisions
•Board approved application by voice vote 4-0.
•Board approved both purchases by voice vote.
•Board approved the MOU unanimously.
•Board approved transfer unanimously.
•Board gave consensus to support DBEDT serving as county point of contact.
•Board will continue monitoring and work with delegation to pursue 2027 legislation.
•Both items approved unanimously.
•Commissioners accepted the report; no formal vote required for information item.
•Contract and budget adjustment approved unanimously.
Directions
•Authorize application submission; accept grant if awarded.
•Award disbursements to be processed by budget and finance following the meeting.
•Award to low bidder and approve budget adjustment.
•Coordinate ceremony and operational details with Jefferson County.
•DBEDT to act as point of contact and send letter of support.
•Encourage residents to contact state delegates (Quarterman, Bridal, Valentine).
•Proceed with documentation and acceptance once Army signs off.
•Procurement to finalize contracts and obtain necessary approvals.
•Procurement to proceed with contract execution; Real Property to accept beneficiary role for grants.
Board of County Commissioners Meeting - August 11, 2026
The meeting of Washington County concluded with a motion to adjourn. The presiding Chair announced a motion to adjourn, which was seconded and carried by voice vote.
Discussion Points
•Chair announced a motion to adjourn and called for a voice vote.
Decisions
•Motion to adjourn carried by voice vote; no opposition recorded in transcript.
Board of County Commissioners Meeting - July 28, 2026
Washington County Board of County Commissioners held a July 28, 2026 regular meeting covering consent approvals, an adequate public facilities mitigation plan for the Rock Springs subdivision, several procurement and intergovernmental purchases, a $1.12 million design task order for a replacement air traffic control tower, and multiple appointments and MOUs.
Discussion Points
•Board previously accepted $1.5M in state funds for the project on June 30.
•Board views concurrence as regional economic support with no fiscal obligation.
•Developer spent ~$300,000 engineering/entitlement and expects $850,000 site development; phase 1 access via Massey Boulevard.
•Elementary district projected to 129.1% capacity with phase 1; AMC proposed to mitigate elementary impacts.
•FTZ activation allows secure storage and customs handling; county uses ~36 of its 2,500‑acre cap.
•Hub City Mobile maintains WordPress plugins and site; bringing another vendor up to speed is costly.
•Items were presented by department staff and county clerk with unanimous approval.
•Most nominated tracts are in Hagerstown; county property in those tracts is largely residential with one 2.5‑acre commercial parcel.
Board of County Commissioners Meeting - July 21, 2026
Washington County Board of Commissioners met in July 2026 to consider multiple land-use and procurement items, approving a water-and-sewer plan amendment for a Mason Dixon Road property, zoning changes for the Fort Richey Special Economic District and two Morgans Avenue parcels, and several capital contracts including elevator replacements and stormwater work.
Discussion Points
•An emailed comment requested more transparency for neighbors.
•Applicant argued the parcels are functionally separate from adjacent residential neighborhood and that increased traffic and commercial development justify rezoning.
•Applicant sought clarity to support light industrial and mixed‑use redevelopment in Fort Richey.
•Board agreed to change but leave a specific setback (19(c)(3)) at its normal distance rather than doubling it.
•County counsel and staff clarified the MDE order applied to a different Williamsport property.
•Medco site characterization is a non‑monetary service that could lead to site improvement grants.
•MS4 awards required to comply with state NPDES permit and represent continuation of prior retrofit work.
•Public commenters raised questions about a Maryland Department of the Environment order and site capacity.
•Public commenters who lived and worked nearby supported the change for safety and business reasons.
•Repeated elevator downtime and ADA/access issues justify replacement over ongoing repairs.
•Staff concluded the request met criteria in the water and sewer plan and comprehensive plan.
•Two emailed oppositions flagged historic preservation and fairness concerns for food manufacturing setbacks.
Decisions
•Adopt text amendment RZ‑26‑002 with modification to 19(c)(3).
•Award elevator contract (4‑0 with 1 abstention) and award MS4 design‑build contracts (5‑0); authorize Medco application (5‑0).
•Board approved RZ‑26‑003 (5‑0).
•Board voted to approve the W S 25‑004 amendment (5‑0).
Directions
•Applicant and staff to proceed with implementation consistent with the amended text.
•Business & Economic Development to submit Medco application and coordinate with airport and public works.
•Engineering to mobilize MS4 projects and track permit credits.
•Planning staff to update records and file any required notices.
•Planning to update official zoning map.
•Public Works to execute elevator contract and schedule modernization.
•Staff to coordinate with Antrim Township Municipal Authority about connection details and confirm capacity allocations.
•Staff to publish map amendments and ensure neighbors are notified about future construction.
•Staff to update ordinance text and clarify how section 4.9 applies to food processing uses.
Board of County Commissioners Evening Meeting with the Town of Boonsboro - June 30, 2026
Town leaders from Boonsboro updated Washington County commissioners on several ongoing infrastructure projects — a road realignment, a reservoir replacement and related work — noting delays from utility relocations and state inspections but a continued goal to finish later this year; the session ended with brief thanks and adjournment.
Discussion Points
•Dean North and Ringley development approvals are contingent on road completion.
•Reservoir replacement uses two 0.5-million-gallon tanks for redundancy; testing and decommissioning of the old reservoir remain to be completed.
•State Highway inspector stop-work items and a 1.5-mile flagging separation rule have delayed Potomac Street work.
•Utility pole relocations by Potomac Edison and Verizon are the main constraint on the Chase 6/Campus Avenue realignment timeline.
Decisions
•No formal policy or budget vote taken; meeting adjourned.
Directions
•Continue coordination with Potomac Edison, Verizon and MDE; proceed with county inspections when utilities are complete.
Board of County Commissioners Meeting - June 30, 2026
The Washington County Board of County Commissioners met on June 30, 2026. Major actions included a 12‑month moratorium on new data center applications after public comment, approval of emergency and capital procurement items (airfield work, vehicles, radios, IT hardware), adoption of an updated Emergency Operations Plan and several grant awards, and the board forwarded agricultural preservation easement rankings to the state.
Discussion Points
•Budget amendment prioritized pension contribution and courthouse reserve
•County Attorney said ordinance would pause acceptance/processing to study infrastructure impacts
•County provides logistical support and disposal assistance
•Emergency procurement necessary due to safety/operational needs at detention center
•Multiple public commenters urged a 12‑month pause and transparency
•Procurements largely via cooperative contracts or contingent on grant awards
•Staff estimated 2–4 of the 16 may be funded based on current state budgets
Board of County Commissioners Meeting - June 9, 2026
Washington County Board of County Commissioners met June 9, 2026, approving multiple procurement and grant actions, funding and contract adjustments for public health and transportation, and authorizing applications for federal grants including a FEMA SAFER firefighter hiring request. The board also reviewed an Open Meetings Compliance Board advisory and recessed into closed session.
Discussion Points
•Airport projects require timely FAA/MAA submissions; runway rehab would keep dimensions but update lighting and overlays.
•County must be employer of record for reimbursement; positions would be county employees, not volunteer company staff.
•Federal SAFER grant covers 75% first 2 years, 35% year 3, full county cost thereafter; staff estimate full county obligation could be ~$2.7M annually.
•LEAD program targets police diversion, peer recovery and targeted case management; success cited low probation violations in recent quarters.
•Medical transport contract handles thousands of one‑way trips annually and is fully state/federal funded; staff described operation and reimbursement flow.
•Practical hiring/training timeline: academy/rookie school length ~26 weeks; hires unlikely on station before many months.
•Sha Walter intersection had 10 incidents in three years; safety improvements include new signal and auxiliary lane.
•Sole‑source procurements were justified by compatibility and obsolescence of existing systems.
Decisions
•All health and transportation contracts approved as presented.
•Approved contingent airport awards; approved road and culvert procurements; approved sole‑source software and detention upgrades.
•Authorized submission of SAFER application; approval vote 4-1 with one commissioner opposed
Directions
•Execute contracts and monitor program metrics; staff to provide updates on outcomes and service volumes.
•If awarded, staff to return with implementation timeline and cost projections for each fiscal year.
•Proceed with procurement awards and schedule public notices for road closures.
•Staff to submit FAA/MAA grant applications and return with documentation upon award.
•Staff to submit SAFER application before deadline and report award outcome to board.
Board of County Commissioners Special Meeting - May 21, 2026
Washington County Board of County Commissioners met to consider a consulting contract for water/sewer service, an amended settlement and mutual release related to Fort Richey/JG Business Link International, and an AFSCME memorandum of understanding extension; all three items passed and the board voted to enter closed session.
Discussion Points
•Amendment extends the MOU five years and adds two departments to step-increase eligibility; union representative expressed appreciation for recent pay-scale adjustments.
•Background of original 2019 settlement and $1,500,000 costs the lessee stated they incurred prior to land transfer; prior county/state grant support to neighboring parcel listed by staff.
•Concern about procurement optics; call for broader search vs. immediate approval.
•Need for countywide study of water and sewer capacity; previous consultants have been used (AquaLaw); distinction between this work and the Planning and Zoning Water and Sewerage Plan.
•Whether the county should require a bond to protect taxpayers if developer fails to complete road/repaving work; responsibility for converting roads to county ownership.
Decisions
•Board approved amendment to settlement with direction to add bond language before final execution.
•Board approved contract with GDMS LLC (3-2).
•Board approved the MOU amendment 5-0 and moved into closed session following the vote.
Directions
•Contract to be funded from water and sewer fund.
•Human Resources to update payroll and step schedules.
•Staff to implement amendment per the MOU timeline.
•Staff to incorporate explicit bond/escrow protections and ensure county approval of final road designs before accepting dedication.
•Staff to produce detailed scope and timeline within 30 days.
Board of County Commissioners Meeting - May 12, 2026
Washington County commissioners held a regular meeting that included adoption of the FY2027 operating and capital budgets (approved 4–1), proclamations for Drug Treatment Court Month and Juror Appreciation Month, updates on a federal purchase of a Williamsport warehouse (federal agency ownership; ICE awaiting design and preparing an environmental assessment), several grant acceptances, a culvert procurement, license agreements for the MLK Center, and multiple board appointments.
Discussion Points
•A proposed amendment to reduce the tax rate from 0.928 to 0.920 and reduce operating spending by 0.5% was introduced and not seconded.
•Commissioners discussed likely year-end overages (estimated ~5 million) and the impact of rising property assessments on tax bills.
•County was not involved in property selection or signatory to NDAs; federal government now owns the property.
•Facility has not seen recent capital improvements; gymnasium is in demand for community programming.
•ICE notified county planning and zoning that it will prepare an environmental assessment and will re-engage consulting parties under Section 106 processes once contractor design is available.
•License form chosen to preserve termination flexibility; county is evaluating capital renovation bids.
•Local drug court opened June 2019; 67 enrollments and 35 graduates reported.
•Maryland Judiciary representatives emphasized grassroots origins and local support as key to problem-solving courts' success.
•Staff reported a general fund total of $355,751,800, capital budget of $103,531,000 and other funds totaling $76,953,560.
Decisions
•Adopt FY2027 budget as presented (4-1).
•License agreements approved (4-1).
•No board action; informational update only.
•Proclamation adopted; graduation to be celebrated later in the week.
Directions
•Budget adopted as presented; CFO to continue expenditure monitoring.
•County to issue press release with information and monitor federal engagement; residents advised to submit comments to federal channels.
•No formal policy action; recognition via proclamation.
•Staff to execute agreements and continue evaluation of renovation bids and longer-term options for the property.
Board of County Commissioners Meeting - May 5, 2026
The Washington County Board of Commissioners conducted routine business, approved eight agricultural land preservation district petitions after a public hearing, approved multiple procurement and hiring actions, and agreed to provide up to $658,290 from county reserves to assist Boonsboro with an urgent waterline replacement (to be reimbursed if grants are received).
Discussion Points
•Commissioners discussed state grants, SHA construction requirements, borrowing options, and urgency tied to fall reservoir online date.
•Engineering procurement noted three bids for inspection services and recommended awarding primary and standby contracts.
•HR explained training and quality assurance needs for dispatchers; ECS coordinator role cited as essential to reduce liability.
•Procurement presented vendor history, number of downloads/responses, and funding availability for Adobe licensing.
•Public commenters supported preservation priorities; one commenter raised unrelated allegations against county officials; another questioned the use of nondisclosure agreements.
•Staff explained program mechanics and fiscal impact (~$12 per acre average for these petitions).
•Town presented technical explanation of line failures, inconsistent repairs and the connection to increased reservoir pressure; town manager said roughly 4,000 people could be affected.
Decisions
•Approve Adobe requirements contract; award construction inspection primary and standby contracts; authorize two hires.
•Approve eight 10‑year agricultural land preservation district petitions.
•Approve funding up to $658,290 with reimbursement condition.
Directions
•County to provide up to $658,290 from CIP reserves, subject to reimbursement if grants are awarded.
•HR to extend offers and complete hiring paperwork.
•Procurement to finalize contracts and upload to procurement portal.
•Staff to add approved properties to program records and notify landowners of application status and next steps.
•Town to apply for state grants (MDE, SHA) and seek state assistance where feasible.
Board of County Commissioners Meeting - April 28, 2026
Washington County commissioners held a public meeting that included three public hearings (airport fees, water/sewer connection fees, and the Community Reinvestment & Repair Fund), multiple procurement and grant approvals, and a motion to place Hancock Rescue Squad under county oversight after an internal review found unpaid invoices and governance weaknesses.
Discussion Points
•Commissioners asked for prior year contract amounts for comparison on some items.
•County staff has been managing mail and payments and recommended a formal MOU to provide fiduciary oversight.
•Funds restricted to ZIP 21740; may not be used for law enforcement; require oversight and reporting.
•Multiple administrative resignations left Hancock with governance gaps and unpaid invoices.
•Public commenters alleged the county should use reserves or improve transparency rather than raise fees.
•Several items were sole‑source because state grants designate specific vendors.
•Staff said fee increases are needed to meet projected infrastructure needs and compliance obligations.
•Staff said insurance costs rose nearly $20,000 and a $2–3M repaving project is planned; parking revenue supports airline model for ultra‑low‑cost carriers.
•Survey (156 respondents) informed priorities: health and wellness; community quality of life; economic opportunity; youth.
Board of County Commissioners Meeting - April 14, 2026
Washington County Board of County Commissioners met April 14, 2026. Staff updated commissioners on a planned federal processing facility at a Wright Road warehouse in Williamsport, county transit FY27 budget concerns, and approved several grants, procurement awards and budget transfers.
Discussion Points
•County Administrator Michelle Gordon briefed the board on DHS/ICE plans for a Wright Road warehouse purchased by the federal government.
•Design grant execution for a transit facility is delayed pending federal grant documents.
•DHS contracted KVG LLC for engineering/construction and indicated the federal government would pay for any required infrastructure upgrades.
•DHS told the county the facility is a processing/booking facility, not a detention center, that it expects ~500 beds in use but sized the facility for 1,500, and that typical detainee stays would average 3–7 days.
•Presenters outlined FY27 transit operating budget and revenue model and warned state contributions are decreasing compared with federal funding.
•Staff proposed new positions and pay reclassification to reduce overtime and improve recruiting/retention.
Decisions
•Consensus to prepare public‑hearing documents and continue advocacy on state transit funding.
•No formal county action taken; the board noted the federal government's ownership and jurisdictional limits.
Directions
•Board to advance the draft budget toward public hearing.
•County staff to monitor communications from KVG/DHS and post information publicly as it becomes available.
•Residents directed to contact federal elected officials for additional information (Congresswoman April McLain Delaney; Senators referenced).
•Staff to provide personnel and overtime worksheets and support materials to commissioners for further review.