The Decatur County Board of Zoning Appeals and Area Plan Commission met Nov. 4, 2026. The zoning board approved a five-year conditional use for a temporary salon structure at 1105 S. State Road 3 (petition Z2026-14). The APC gave a favorable recommendation on proposed building permit and inspection fee changes (ordinance 2026-2) and moved a revitalization show-cause hearing to court in January.
Discussion Points
•Applicant requested postponement to the Dec. 2 meeting.
•Applicant will use existing driveway and connect to existing septic and Westport water.
•Commissioners debated fairness for low‑inspection commercial uses like cold storage and whether outside inspection fees should alter local charges.
•Court calendar is full; likely hearing in January.
•Freestanding signage requires separate application and may need state approval on a state highway.
•Respondent Charity Phillips did not appear; staff described vegetation and a deteriorating structure and noted an open permit.
•Staff summarized fee updates, noting last changes were in Jan. 2015 and that new‑home per‑sq‑ft rate would rise.
•Temporary building is on skids and will be insulated; planned to be family-operated with limited clients.
Decisions
•APC gave a favorable recommendation on ordinance 2026-2; motion passed with one dissent.
•APC moved R2026-40 to court for enforcement hearing.
•APC petition 2026-19 tabled to 12/02/2026.
•Five-year conditional use approved for petition Z2026-14.
Directions
•Applicant to consult county office on signage and state highway permitting.
•Clerk to schedule item for Dec. 2 APC meeting.
•Staff to prepare clarifications on how outside plan-review/inspection fees interact with local fee increases.
•Staff to schedule court hearing and continue outreach to property owner.
Decatur County commissioners held a regular meeting covering highway department updates (including a proposed traffic study for 0421, INDOT reimbursements and grants), several APC rezoning approvals, adoption of a county comprehensive plan after debate over alternative-energy language, a proposal to consolidate voluntary employee insurance with American Fidelity, and discussion of annex renovations and financing options.
Discussion Points
•Alternate prices for ceiling-tile replacement (~$331,628) and EMA training room (~$81,000)
•APC recommended rezoning of multiple small parcels to allow primary residences
•Balance sought between protecting agriculture and allowing future-technology exceptions
•Concerns about grandfathering existing employee plans and rate changes
•Direction to seek financing analysis for annex renovation
•Key policy decision: adoption of comprehensive plan
•Need for apples‑to‑apples comparisons and payroll deduction logistics
•Need for a traffic study on 0421 to assess speeds and vehicle classes
•Numerous routine administrative approvals
•One commissioner abstained due to family relationship
•Possibility of temporary winter repairs vs. permanent spring repairs
•Question to INDOT about reimbursement for unofficial detour routes
•Recommendation to consolidate voluntary insurance to a single vendor (American Fidelity)
•Recommendation to request Baker Tilly financing analysis up to $25,000
•SD Barnes responsive bid for annex exterior renovations (~$1.0M)
•Steering committee and public review included debate about alternative-energy language
Decisions
•Adopt comprehensive plan as written
•Adopt comprehensive plan; defer insurance consolidation; forward annex bid to council
•Defer final decision to Nov. 16 commissioners meeting
•Proceed to council with bid and Baker Tilly financing analysis request
•Resolutions/motions to approve each petition carried
Directions
•File resolution, obtain vendor comparisons, and present financing options to county council
•File the resolution and process advertising/close-out items
•Forward bid to county council and commission Baker Tilly to prepare financing options
•Obtain detailed rate and coverage comparisons from American Fidelity and provide employee outreach plan
•Sign and file APC paperwork; update county records
•Staff to solicit quotes from traffic consultants and return with cost estimates and vendor recommendations
The Decatur County RDC approved minutes and its 2027 annual spending plan, agreed to send a conditional letter supporting a sewer-extension commitment for the Adams Rail Park prospective project, scheduled its next meeting for Nov. 18 and then adjourned.
Discussion Points
•Chair called for additions/corrections to minutes; none were raised.
•Chair distributed 2027 spending plan and noted materials explaining disbursements.
•Committee members requested conditional/limited funding language to avoid open-ended financial exposure.
•Staff requested RDC willingness to commit to extending sewer utility; staff noted extension is ~1 mile and ties to existing force main.
Decisions
•Approve 2027 annual spending plan.
•Approve prior minutes; adjourn meeting.
•Send draft conditional commitment letter regarding sewer extension to Adams Rail Park project.
Directions
•Approve sending the draft letter with allowance for wordsmithing; staff to circulate and file final copies.
•File the approved plan with county commissioners and the state.
•Set next meeting for Nov. 18 (third Wednesday in November).
Decatur County commissioners approved routine business including minutes, claims and payroll; awarded $31,222.70 from opioid settlement funds to the county EMS for upgraded CPR devices; heard updates on public health grants, highway projects and veterans outreach.
Discussion Points
•Commissioners confirmed paperwork and expressed support.
•Decision to increase invoice payment for seized cattle to reflect larger herd size.
•Durban described grant amount and line items ($597 training; $803 materials).
•JRAC representative presented settlement totals and breakdown of restricted/unrestricted funds.
•Justin reported multiple road projects, temporary patching and grant plans.
•NDOT approved Bridge 131 right-of-way contract; RFPs for inspection will follow.
•Noted $80,000 contingent award to ARC remains unresolved.
•Plans to move Veterans Day appreciation to the veterans office and hold recognition during a Decatur County High School game.
•REDI II projections presented with larger private-investment targets.
•REDI I outcomes reported: leveraged private investment, job creation, childcare seats and housing units.
•Request for $31,222.70 to purchase CPR devices for two ambulances; board discussed funding source.
•Routine approvals of minutes, claims and payroll.
•Tim Ortman accepted the superintendent role.
•VA-related economic impact rose from $14.5M to $19M for FY2025.
Decisions
•Appointment accepted; projects and grant planning to proceed.
•Approval to implement Safe Sitter program using the grant.
•Award of $31,222.70 to Decatur County EMS approved.
Decatur County Council met to approve personnel and budget items, including a salary increase for the SVO/violent-offender registry coordinator, a PERF correction to add the coroner retroactive to 2015, grant approvals, and the county budget; several appointments and community proclamations were also approved.
Discussion Points
•A budget form typo left the public-defender request smaller than intended by $26,525.
•Chair read fund totals and highlighted a 27th pay period that will affect 2028 budgets.
•Company representative cited construction delays, industry pullback and lower sales forecasts as reason to delay abatement.
•Coordinator duties expanded to field enforcement and solo home visits; significant specialized training logged in 2025–26; coordinator generated investigations leading to charges and convictions.
•Council asked staff to post details on the county website and coordinate with the foundation.
•Discovery that coroner had been omitted from a prior PERF resolution dating to 2014–15; two employees affected; PERF must approve amounts.
•EMPG is a reimbursement grant for salaries with an additional $5,500 cited for FY26; the application window was short and staff completed paperwork.
•Health Department requested $1,400; accepted.
•Judge proposed using supplemental public-defender fund; county typically receives 40% reimbursement for public-defender salaries, which will replenish the fund over time.
•Proclamation text read; Community Foundation to cover shipping costs using Ella Jo Briggs Fund.
•Question whether reclassification should be routed through HR and job description updated before pay implementation.
•Some members asked clarifying questions about salaries and pay-period calculations.
•Staff clarified the real/property vs personal-property start dates and abatement terms (7 years and 5 years respectively).
•Staff to collect signatures and submit paperwork to PERF; county will report back once PERF provides totals.
Decisions
•Both grants approved by council.
•Budget adopted at $33,813,818.
•Council approved enlargement resolution 2026-16 to include coroner retroactive to 2015.
•Council approved the adjusted start date; one member abstained.
•Council approved use of supplemental fund to cover the $26,525 shortfall.
•Proclamation approved by voice vote.
•Salary increased to $57,000; classification remains a special-deputy operational role pending HR review.
Directions
•County Communications to publish proclamation and collection details.
•Emergency Management to submit reimbursements and track expenditures per grant rules.
•Finance to publish final adopted budget and notify departments to account for 27th pay period.
•HR to receive updated job description and classification for review.
•Staff to sign and send the enlargement resolution to PERF; return with total amounts if required.
•Staff to update abatement paperwork to reflect 2027 start and 2028 payments.
•Treasurer/accounting to transfer funds to cover salaries immediately and report back.
Decatur County Area Plan Commission considered multiple rezoning and variance petitions, granted several that will move to the county commissioners, held a show‑cause hearing and extension to court on an ordinance violation, and held a public hearing on the Decatur County draft comprehensive plan with extensive public comment focused on alternative energy and data centers.
Discussion Points
•Applicant intends a single‑family home; access will be via an easement to the east; driveway permit needed.
•Applicant noted purchase offer contingent on rezoning; staff confirmed sanitary and driveway preliminary approvals.
•Applicant plans a single‑family residence; access via lifetime easement; board urged clarity on maintenance responsibilities.
•Board reviewed proposed additions, potential encroachment compared to existing southwest corner, and site constraints including electrical panel.
•Questions focused on driveway access and parent parcel access after division.
•Respondent disputed receipt of earlier notice dates and said cleanup is ongoing; staff confirmed sheriff service dates and prior notices.
•Whether to use 'generally discouraged' vs 'not permitted' vs 'prohibit' in reference to alternative energy on agricultural land; moratorium extension for ordinance drafting; water use and flood concerns related to data centers.
Decisions
•Extension granted to end of November; staff authorized to file cause if noncompliance continues.
•Favorable recommendation forwarded with edit; steering committee to revisit wording; staff to draft ordinances in parallel.
•Rezoning recommendation approved by APC.
•Rezoning recommended to commissioners.
•Variance approved; move to permitting process.
Directions
•Advised petitioner to coordinate with county office for building permit and inspections.
•Applicant to apply for driveway permit and correct documentation.
•Applicant to confirm easement maintenance responsibilities; pursue driveway permit.
•Applicant to secure driveway permits and clarify easement maintenance.
•Authorize county staff to proceed to schedule case for November 27 court date and to take photographs for evidence.
•File forwarded to commissioners for final action.
•Strike 'permitted for good cause' in the plan's relevant sentence and send wording back to steering committee; commissioners to consider extension of moratoria and ordinance drafting.
Decatur County commissioners met Oct. 5, 2026, and approved routine business, awarded contracts and purchases (including four dump trucks), approved a records-redaction contract for police video, authorized an EMPG grant application, approved a deed-sale addendum for 23 Lake McCoy parcels, and selected a highway superintendent candidate.
Discussion Points
•Alternate providers may require additional months of claims history to quote
•Bid comparison: International lowest at $254,501.25 vs Peterbilt $277,717 per truck
•Board favored candidate C based on interviews and experience
•County has previously spent consultant money repeatedly to offer properties for sale
•Dunn proposed a roughly 1% premium increase
•Dunn provides combined claims and brokerage services and local points of contact
•EMPG reimburses staff and match; typical prior award around $30,000
•Enforcement: sheriff said stops would likely occur past Honda or at enforcement choke points
•Exemptions: local destinations and permitted oversized loads should be allowed
•Four candidates interviewed; multiple candidates had strengths
•High volume of video requests (69 this year; 68 with video)
•Low bid was $26,442.40 from Dull Spray Foam & Insulation
•Manual redaction takes roughly eight staff-hours per hour of footage
•Most properties suffer tangled lot lines and survey uncertainties
•Need to balance triaxle vs tandem trucks for winter plow lines and cul-de-sacs
•Payment and invoicing logistics to split across fiscal years
•Proposed Axon tool costs $4,028 and requesters pay $150 per video
•Reimbursements usually come 6-8 months after fiscal year
•Scope and duration: preserve asset between Honda and Love's
•Tentative amount for upcoming cycle appears to be $35,500
•Three bids received for spray-foam insulation to address condensation-related ceiling damage in clerk's office
•Venting and after-hours work were discussed to mitigate disruption
•Waste station and utility issues make immediate occupancy or resale risky
Decisions
•Application authorized
•Candidate C selected; offer to be extended
•Contract approved
•Contract awarded
•Deed-sale addendum approved for 23 parcels
•Four trucks approved, two paid from current year, two from next year
•No ordinance introduced; further study directed
•Remain with Dunn for another year
Directions
•Award contract to low bidder and coordinate schedule with clerk's office
•EMA to apply for EMPG
•Offer position to candidate C and have staff follow up
•Proceed with purchase order; use half payment this year and remainder upon chassis inspection when available
•Procure Axon redaction capability; fund from accident fund and rely on requester fees to offset cost
•Staff to research ordinance language and enforcement logistics, consult sheriff and follow up in the spring of 2027
•Stay with Dunn for 2027; research alternatives earlier next year
•Take deeds and commission surveys to create clear parcels for resale
The Decatur County commissioners approved highway staffing and truck purchases, a video-redaction contract, a grant application, property and insurance items, courthouse insulation work and a new highway superintendent. They also reviewed routine financial approvals and received department updates.
Decisions
•The commissioners unanimously approved the September 21 meeting minutes, claims as presented and payroll of $424,557.30 for September 25, 2026.
Decatur County commissioners met Oct. 5, 2026, and approved routine financial items, several procurement and personnel actions, and grants. Major items included approval to buy four dump trucks, selection of a new highway superintendent (Candidate C), a redaction-license purchase for body/dash camera video, and contracts for courthouse insulation.
Discussion Points
•Asphalt plant closures limit paving options until spring; temporary repairs will be used until then
•Condensation and water damage reported in clerk’s office
•Deed-sale addendum covers 23 properties at Lake McCoy
•Discussion focused on parcel complications and maintenance burdens
•EMA anticipates about $35,500 in EMPG salary reimbursement
•Four candidates interviewed
•Insurance committee presented Dunn and Associates renewal with 1% increase
•Manual redaction is time-consuming (~8 hours per 1 hour of video)
•Multiple forthcoming retirements may cause staffing shortages during snow season
Routine Decatur County commissioners meeting on Oct. 5, 2026, where attendees approved minutes, payroll and multiple contracts; discussed highway staffing and equipment needs, awarded several contracts and selected a new highway superintendent; several departmental updates were provided.
Discussion Points
•23 properties included in deed sale addendum
•69–80 public-records video requests this year
•All motions carried unanimously as recorded
•Anticipated EMPG funding approx. $35,500
•Area Plan announced comprehensive-plan hearing Oct. 7 with four petitions
•Asphalt plant closures require temporary repairs until spring paving
•Axon quote of $4,028 for redaction licenses
•Committee recommended staying with current carrier
•Condensation and water damage in clerk's office
•EDC reported regional economic development and conventions
•Four candidates interviewed
•Longstanding parcel complications and maintenance burdens discussed
•Motion to select Candidate C for highway superintendent
•Multiple retirements could produce staffing shortfalls before snow season
•Multiple routine approvals including payroll of $424,557.30 and contracts
•Notify Now has ~800 enrolled contacts
•Redaction requires roughly eight hours per hour of footage
•Renewal shows 1% increase
•Salt inventory is approximately 1,710 tons
•Three bids received with lowest at $26,442.40
Decisions
•Addendum approved
•All recorded motions approved unanimously
•Application authorized
•Axon contract approved
•Bid accepted; work to be scheduled before year-end
•Candidate C selected; HR to extend offer
•Hiring motion approved; four dump trucks ordered
•Renewal approved
Directions
•Accept lowest bid and schedule work
•Apply for EMPG Salary Reimbursement grant
•Approve addendum to resolve title and maintenance issues
•Approved two hires to fill upcoming vacancies
•Departments to proceed with contract execution, HR to contact superintendent candidate, EMA to submit grant application
•HR to reach out to Candidate C with job offer
•Proceed with Dunn and Associates renewal for 2027
•Procure four dump trucks with funding split across budgets
Regular Decatur County Commissioners meeting on Oct. 5, 2026: commissioners approved routine financial items, multiple procurement contracts (including four dump trucks and courthouse insulation), authorized a body-camera redaction license, approved a grant application, and selected a highway superintendent candidate.
Discussion Points
•69–80 video public-records requests this year.
•Anticipated EMPG funding approx. $35,500.
•Asphalt plant closures limit paving; temporary repairs planned until spring.
•Commissioners selected Candidate C by motion.
•Condensation and water damage reported in the clerk's office.
•Equipment shortfalls addressed via truck purchases and hiring.
•Four candidates interviewed for Highway Superintendent.
•Insurance committee recommended renewal with Dunn and Associates; 1% increase reported.
•Longstanding parcel complications and property-line issues at Lake McCoy.
•Maintenance burdens discussed.
•Notify Now has about 800 enrolled contacts.
•Redaction estimated at eight staff-hours per hour of video.
•Review and approval of prior meeting minutes and claims.
•Salt inventory approx. 1,710 tons.
•Three bids were presented with the low bid at $26,442.40.
Decisions
•Application authorized.
•Axon license approved.
•Candidate C selected; HR to extend offer.
•Contract awarded to Dull Spray Foam & Insulation.
Decatur County commissioners approved a temporary moratorium on new hyperscale data centers, heard reports on road and planning projects, received updates on a cattle seizure and veteran services, and tabled a courthouse filming request pending insurance and liability details.
Discussion Points
•126 new client entries into state software; $14,000,000 in VA benefits flowing to county residents; encouragement to refer veterans for assistance.
•Edits completed and distributed; public outreach included meetings and online surveys; ordinance drafting to follow plan completion.
•Graffiti removal approach (pressure wash vs. paint); INDOT schedule for structure replacement; dust-control test using calcium chloride; road salt procurement (60 tons).
•Insurance, waivers, worker's comp and roster required; limit production to first floor due to confidential records upstairs; sheriff staffing and potential costs must be addressed.
•Martin volunteered for the role; no objections recorded.
•Multiple routine approvals by voice vote; data-center moratorium adopted as a substantive ordinance; one filming request tabled pending documentation.
•Pretrial date (Oct. 13) and trial date (Nov. 12); request to increase payment for animal care; herd count increased to 63.
•Scope of 'hyperscale' threshold set at 250 MW to capture large sites; annexation removes county jurisdiction; concerns about water and discharge capacity in rural areas.
•Area Plan Board public presentation on Oct. 7; staff to solicit ordinance-drafting work after plan completion.
•Highway staff to coordinate closures with local businesses and continue dust-control trials.
•Publicize veteran-service resources; connect veterans to County Veteran Service Officer.
•Publish moratorium, notify applicants, and follow up on filming documentation.
•Publish ordinance text; continue comprehensive-plan and ordinance drafting; coordinate with Area Plan Commission.
•Require production provide proof of insurance, waivers, roster and agree to reimburse county staffing costs; staff to inform applicants and return with documentation.
•Shelter staff to work with county attorney and report back.
The Decatur County commissioners met Sept. 21, 2026, to review county operations, hear department updates and approve a temporary moratorium on certain large data-center applications. They also discussed road work, the comprehensive plan, veterans services, emergency notifications and other county matters.
Discussion Points
•Cash Bash proceeds support small-business grants; four $1,500 grants were awarded last year.
•Code Red users must sign up again; Code Red will be deactivated after a brief transition.
•Commissioners said current local ordinances, zoning and planning do not adequately address hyperscale growth.
•Crews planned temporary bridge-jumper removal and reinstallation for harvest travel and the last superload.
•Gabe Nobbe said he did not support a large-scale data center because of resource demands.
•More than $14 million in VA benefits was reported for county residents, excluding Department of Defense benefits.
•Notify Now was active and had more than 600 enrollees in its first week, excluding an unreported Fall Festival count.
•Payroll presented for approval totaled $427,066.86 for Sept. 11, 2026.
•Radius mapping work began for a new 911 system intended to integrate with Vesta 911.
•READI Two had spent nearly or more than half its funds and READI One projects were nearing closeout.
•Regional representatives planned commercial and retail investment outreach.
•St. Paul was seeking an OCRA grant for sewer issues, with residents’ accounts and photographs potentially supporting the application.
•The Chamber reported planned ribbon cuttings, an annual dinner and Cash Bash ticket details.
•The commissioners discussed whether to install cameras at the covered bridge.
•The county attorney identified documentation and cost requirements for any approval.
•The filmmaker’s proposed courthouse use was expected to take place in the evening for about four or five hours.
•The moratorium applies at 250 megawatts or greater and is aimed at hyperscale data centers.
•The representative attended to meet the statutory compliance requirement for the county veteran service officer.
•The revised plan was distributed after edits following the Sept. 3 steering committee meeting and public presentation.
•The shelter contacted its attorney and had not received a response.
•Verbal requests concerned the amount paid to care for the cattle.
•The commissioners unanimously approved the courthouse lawn display request.
•The commissioners unanimously approved the Sept. 8 meeting minutes, Sept. 11 executive-session minutes, claims, payroll and Larry Martin’s recommendation for the Sandcreek Township Advisory Board.
Directions
•The Area Plan Commission’s ordinance work was to begin after completion of the comprehensive plan.
•The filming request remains tabled until required information and documentation are received.
Decatur County commissioners imposed a temporary moratorium on hyperscale data-center applications through Dec. 31, 2026, while the county finishes its comprehensive plan and drafts new standards. The meeting also covered highway work and closures, an animal-shelter cattle case, activation of a new emergency notification system, and several routine approvals including an appointment to the Sandcreek Township Advisory Board.
Discussion Points
•250 MW chosen as threshold as a low-end hyperscale cutoff; many hyperscale centers are larger.
•Area Plan Commission public presentation scheduled for Oct. 7; commissioners to hold a hearing in November if favorable recommendation received.
•Bridge jumper removal schedule and brief reinstall for last superload.
•Code Red registrants must re-register; Code Red will be deactivated.
•County Road 350 West intersection closure and left-turn restriction schedule.
•Edits to the comprehensive plan completed after Sept. 3 steering-committee meeting.
•Estimated $14 million in VA benefits coming to county residents; excludes DoD benefits.
•Hearing schedule for cattle case (pretrial Oct. 13; trial Nov. 12).
•Herd size increased to 63 animals; residents asked about care costs.
•Ken Mobley entered 126 new clients into state-supported system.
•Minutes, claims and payroll approved by unanimous vote.
•Need to pause acceptance of hyperscale data-center applications to allow planning and ordinance drafting.
•Notify Now launched; >600 enrollees in first week.
•Right to Life lawn permit approved; filmmaker request tabled pending insurance and waivers.
Decatur County commissioners met Sept. 21, 2026. They approved routine minutes, payroll of $427,066.86, several permits and an appointment, adopted a temporary moratorium on hyperscale data-center applications through Dec. 31, and received updates on roads, the comprehensive plan, an animal-shelter cattle case, veterans benefits, and a new county emergency-alert system.
Discussion Points
•Commissioners said current local ordinances do not adequately address hyperscale data-center growth and set the moratorium to allow standards drafting.
•County Attorney outlined insurance and staffing-payment requirements for private filming on courthouse property.
•Edits completed; Area Plan presentation scheduled Oct. 7.
•Higgins praised Mobley for entering 126 new clients and for the scale of VA benefits reaching county residents.
•If Area Plan issues favorable recommendation, commissioners will hold a public hearing in early November.
•Notify Now activation; more than 600 enrollments first week; Code Red users must re-register.
•Pretrial Oct. 13 and trial Nov. 12 scheduled for the cattle case; herd size reported at 63.
•Radius mapping for new 911 system begun to integrate with Vesta 911.
•Removal and temporary reinstallation of bridge jumpers to accommodate harvest and a final superload.
•Routine approvals, payroll total of $427,066.86, appointment of Larry Martin, Right to Life event approval and tabled film request with required paperwork.
•Shelter has contacted its attorney for next steps.
Decisions
•Adopted Ordinance 2026-15, moratorium through Dec. 31, 2026.
•Approved minutes, claims, payroll and permits as recorded; tabled film request.
Directions
•Area Plan to begin ordinance work after completion of the comprehensive plan; Area Plan contacted three firms for ordinance work.
•Area Plan to present Oct. 7; ordinance drafting to follow comprehensive-plan completion.
•Filmmaker request remains tabled until requirements satisfied.
Decatur County commissioners met Sept. 21, 2026, and approved routine financial items, adopted a temporary moratorium on large-scale data-center applications (Ordinance 2026-15), reviewed highway work schedules including a road closure Oct. 6–15, heard updates on the comprehensive plan, the animal-shelter cattle case, veterans services, and county emergency-notification rollout.
Discussion Points
•Bridge jumper removals to accommodate farm equipment; covered bridge restoration completed; U.S. 421 work nearing finish; County Road 350 West intersection scheduled for closure Oct. 6–15.
•Commissioners said current ordinances do not adequately address hyperscale data centers and that 250 MW is at the low end of hyperscale.
•Edits completed after steering committee meeting; revised plan distributed to Area Plan Commission.
•Ken Mobley entered 126 new clients into state system; more than $14 million in VA benefits expected for residents.
•Notify Now activated; more than 600 enrollments in first week; Code Red users must re-register; radius mapping for Vesta 911 in progress.
•Pretrial set for Oct. 13 and trial for Nov. 12; shelter contacted attorney; herd increased to 63 cattle.
•Right to Life request approved for Oct. 3–10; film request tabled pending insurance and waivers.
Decisions
•Adopt Ordinance 2026-15 moratorium through Dec. 31, 2026.
•Approve Right to Life, table film request.
Directions
•Area Plan to hold public presentation Oct. 7.
•Area Plan to solicit and engage consultant(s) to draft data-center standards after comprehensive plan is completed.
•Film production must provide proof of insurance, rosters, waivers and workers' compensation and cover county staffing/overtime costs.
The Decatur County commissioners met on Sept. 21, 2026, and unanimously approved a temporary moratorium on hyperscale data centers while the county finishes an updated comprehensive plan; other items included road and bridge work schedules, an ongoing animal-shelter cattle case with trial dates, a veterans-services update citing about $14 million in benefits for residents, and rollout of a new county emergency notification system.
Discussion Points
•Amount excludes DoD benefits such as retired pay and TRICARE
•Area Plan public presentation scheduled Oct. 7
•Board said 250 MW is low end for hyperscale and many centers exceed 1 GW
•Commissioners plan their public presentation/hearing at first November meeting if no further changes
•County Road 350 West intersection closure scheduled Oct. 615
•Covered-bridge restoration completed as described
•Edits to the comprehensive plan completed after Sept. 3 steering-committee meeting
•Herd grew to 63 animals, up from 5859
•Measure not intended to block traditional businesses or smaller data centers
•Mobley entered 126 new clients into the state-supported system
•Notify Now active with 600+ enrollments in first week
•Ordinance intended to give time to finish comprehensive plan and draft standards
•Over $14 million in VA benefits expected to flow to Decatur County residents
•Pretrial hearing Oct. 13 and trial Nov. 12 for cattle case
•Radius mapping work initiated to integrate with Vesta 911
•Removal and temporary reinstallation schedule for bridge jumpers
•Residents enrolled in Code Red must re-register
•Shelter contacted attorney but had not received a response
•U.S. 421 structure-replacement nearing completion with October target
Decisions
•Adopt Ordinance 2026-15 (moratorium)
Directions
•Area Plan Commission to contract ordinance drafting firms
•Complete comprehensive plan by Dec. 31, 2026
•Deactivate Code Red once migration is complete
•Encourage residents to register for Notify Now via EMA and county communications channels
•Notify public of closures and detours
•Plan for county public presentation and hearing in early November
•Proceed to Area Plan presentation Oct. 7
•Reconsider cameras on covered bridge only if problems recur
Decatur County commissioners on Sept. 21 approved routine minutes, payroll and claims; adopted a temporary moratorium on hyperscale data-center applications through Dec. 31, 2026; heard updates on road and bridge work and the comprehensive plan timetable; and received reports on the animal shelter and veterans services.
Discussion Points
•250 MW threshold chosen as a lower bound for hyperscale definition.
•Area Plan Commission public presentation scheduled for Oct. 7.
•Cattle-case pretrial Oct. 13 and trial Nov. 12.
•Commissioners will hold their public presentation/hearing at their first November meeting if Area Plan recommends without changes.
•Covered-bridge restoration completed; cameras unlikely at this time.
•Edits completed after Sept. 3 steering-committee meeting and public presentation.
•Exemption for timely-filed petitions/applications.
•Figure excludes Department of Defense benefits such as military retired pay and TRICARE.
•Herd size reported at 63 cattle, up from 58–59 estimates.
•Ken Mobley entered 126 new clients into the state-supported system.
•More than $14 million in VA benefits is coming to Decatur County residents, roughly split between compensation/pensions and VA health care.
•Need for standards addressing construction, maintenance and decommissioning of hyperscale data centers.
•Notify Now enrollment topped 600 in its first week; Code Red users must re-register.
•Planned closure of County Road 350 West Oct. 6–15 for structure replacement.
•Radius mapping work begun for new 911 mapping system to integrate with Vesta 911.
•READI Two spending is notable; READI One projects being closed out; St. Paul seeks a $750,000-per-acre OCRA grant.
•Shelter contacted attorney; no response yet.
•Temporary removal and brief reinstallation of bridge jumpers to accommodate harvest and a final superload.
Decisions
•Adopt moratorium Ordinance 2026-15 through Dec. 31, 2026 at 5 p.m.
Directions
•Area Plan to obtain quotes and draft ordinance language after comprehensive plan completion.
•Proceed with Area Plan presentation on Oct. 7; prepare for commissioner hearing in November if recommended.
Decatur County commissioners on Sept. 21 approved a temporary moratorium on hyperscale data-center applications, reviewed highway work and closures for fall, heard that more than $14 million in VA benefits is flowing to county residents, and received updates on READI funding, chamber events and emergency notification rollout.
Discussion Points
•Bridge jumper removal to facilitate farm equipment during harvest; brief reinstallation Oct. 6–9 for last superload.
•County zoning and planning do not currently address hyperscale data-center growth; 250 MW threshold chosen as a low-end hyperscale marker.
•Covered bridge received pressure-wash and targeted painting; cameras unlikely due to monthly fees.
•Film request tabled pending documentation and insurance per county attorney guidance.
•Herd size reported at 63 animals; shelter sought attorney guidance and had not received a response.
•Ken Mobley entered 126 new clients into the state-supported veteran system.
•Moratorium provides time to complete comprehensive plan and draft standards; petitions filed before enactment are exempt.
•More than $14 million in VA benefits is coming to Decatur County residents; figure excludes DOD benefits.
•Notify Now active with 600+ enrollments in its first week.
•Pretrial Oct. 13; trial Nov. 12 for the cattle case.
•Radius mapping work has begun to integrate with the Vesta 911 system.
•READI Two has spent approximately 50% of its funds; READI One projects are closing out.
•Representatives to attend national retail events to promote Greensburg.
•Residents must re-register if they were on Code Red; Code Red will be deactivated after transition.
•St. Paul seeks an OCRA sewer grant; commissioners noted a request of $750,000 per acre.
•U.S. 421 structure work nearly complete at the south end; next work zone moving north toward 100; County Road 350 West intersection closure scheduled Oct. 6–15.
Decisions
•Multiple motions approved unanimously; film request tabled.
Decatur County commissioners met to review department budget submissions, approve an overall salary schedule based on an outside payroll study, authorize a $1,813,000 appropriation for a solid-waste facility (rescinding a prior $800,000 item), discuss health-department grant-funded positions and vaccine billing changes, and make several line-item budget cuts and transfers.
Discussion Points
•Breakdown of the larger appropriation into lease, construction and operations
•Concern about preserving funds to meet scheduled jail debt payments
•Departments must manage finite part-time budgets
•Estimated cost (~$10.6M) and recruitment/retention implications
•Grant-funded positions and sustainability beyond grant term
•Grant-funded positions and sustainability of funded roles
•Need for program impact/ROI documentation
•Need to correct paperwork to match the consolidated vote
•Potential revenue from buying vaccines directly and billing insurers
•Proposed reductions to bridge replacement and culvert budgets
•Whether the $800,000 item was standalone or part of a larger $1,813,000 appropriation
•Whether to apply a flat percentage raise vs. bring employees up to consultant base and pay stipend