Citizen Portal
Sign in
Front PageNationalFollowingFavorites
Front of the Wayne County Courthouse , located along U.S. Route 40 (S. A Street) in downtown Richmond , Indiana

Photo: Nyttend·Public domain·via Wikimedia Commons

Friday, November 13, 2026
Indiana / Wayne County / Richmond

Richmond

OverviewMeetingsDataOfficials
Population
35,5812024
Higher than communities in Indiana
Household income
$45,3992024
Less favorable than communities in Indiana
Home value
$114,4002024
Similar to communities in Indiana
Unemployment
4.2%2026
Similar to communities in Indiana
Violent crime
5402012
Less favorable than communities in Indiana
Work from home
4.7%2024
Similar to communities in Indiana
Source: Polco GPAL, using data from the original source shown for each indicator.Data from Polco

Meetings

Loading meetings…

Richmond, Ind.

Open map →
Wayne County, Indiana · Census county shapes

Quick actions

Richmond officials

All officials →

Hot topics in Richmond

  1. 1 Flock Safety Cameras
  2. 2 Data Center Development
  3. 3 Short-Term Rental Rules
  4. 4 Property Tax Rates
  5. 5 Homeless Encampments
See more →
Citizen Portal
See government, clearly.
Platform
About usFor citiesTopicsNewsDiminished Fourth Estate
Support
Help center
Community
Affiliate programSupport CPVolunteer
Legal
PrivacyTerms
Find your state
ALAKARAZCACOCTDEDCFLGAHIIAIDILINKSKYLAMAMDMEMIMNMOMSMTNENHNJNMNVNYNCNDOHOKORPARISCSDTNTXUTVAVTWAWIWVWYPRGUASVI
© 2026 Citizen Portal. Meeting records and summaries sourced from the public record.
37°F (3°C)
Cloudy · H 44° L 35°
20 meetings
11
Nov

City of Richmond Sanitary District Board of Commissioners of November 10, 2026

Indiana//Richmond City

The Richmond Sanitary District Board of Commissioners met Nov. 10, 2026, approved routine minutes, invoices and multiple procurement items, heard a director's report on leaf collection, televising and recycling changes, approved several contracts and permits, and authorized a memorandum of understanding with IU East to test E. coli sources. The board also approved an amendment to a levy-certification contract split with the Stormwater board.

Discussion Points

  • •Board asked for any questions; none were raised.
  • •claims_matrix
  • •clarifying_details
  • •clarifying_details_array_stub_removed_for_size
  • •clarifying_details_placeholder_removed_for_schema_limits_but_entries_exist_in_internal_recording
  • •community_relevance
  • •directions':['Refer bids and quotes to management for tabulation and recommendation.'],'decisions':['Approve change order to Oler Fencing ($450) and award grading/railing update to Apex Ag Solutions.']},
  • •Director described IU East's ability to analyze E. coli and attribute likely sources (human vs. animal).
  • •Director explained increased televising, differences between street-department and district leaf collection, recycling operational change to auto-sort, and timeline for can distribution.
  • •Director explained Sourcewell contract discount, parts compatibility, and expanded order to reach more households.
  • •_editorial_flag_removed_for_schema_conformance
  • •engagement_forecast
  • •graph_signals
  • •highlights
  • •_internal_quiet_notes_removed_for_final_output_restrictions_if_any
  • •meeting_context
  • •_note_truncated_for_compactness_in_schema_usage_allowed_by_system_error_handling_if_needed
  • •_placeholder_end_marker_removed_since_schema_requires_valid_json_object_only
  • •proper_names
  • •proper_names_array_stub_removed_for_size
  • •provenance
  • •salience
  • •searchable_tags
  • •Staff described levy certification process and construction completion; recommended contract amendment and cost-sharing with Stormwater.
  • •Staff read bid totals and quote validity periods; one change order explained operations need for a manual main gate.
  • •Staff summarized scope: asset inventory, plan update and master planning for future capital needs; new legislation prompted part of the update.

Decisions

  • •Approve amendment #3 to contract 97-2018 for an additional $69,100; split 50/50 with Stormwater.
  • •Approve invoices totaling $468,890.66.
  • •Approve purchase agreement with Pyramid Equipment for $146,324.69.
  • •Enter into agreement with Commonwealth for the two-part effort.
  • •Recommend approval of MOU; motion carried.

Directions

  • •Coordinate split billing and proceed with certification efforts.
  • •Proceed with asset-management update funded in 2026; issue PO for master plan in 2027.
  • •Staff to collect samples and arrange processing with IU East under MOU.
  • •Staff to place order and phase distribution starting March 2027.
  • •Staff to update future reports with aggregate tons and breakdown estimates.
5
Nov

Richmond Board of Public Works Meeting of November 4, 2026

Indiana//Richmond City

Richmond City Board of Works and Safety met Nov. 5 to approve minutes and routine claims, grant two handicap parking sign renewals, authorize a street closure for antenna work at 630 E. Main St., adopt several personnel and IT contracts, approve a police shift-length addendum, and acknowledge fire merit commission election results.

Discussion Points

  • •Articles 17B, 18 and vacation leave language affected
  • •Bargaining unit ratified contract by 90%
  • •Merit system language pending
  • •No substantive debate recorded
  • •Officer inspected both sites and found ordinance compliance.
  • •Project is replacement of existing antenna of same size/height
  • •Proposed dates Nov. 9 (all day) and Nov. 20 (approx. four hours)
  • •Recommendation to stagger initial terms under Indiana Code 36‑8‑3.57
  • •Routine approval of minutes and claims
  • •Three‑year term at $60,750 annually
  • •Union picks Tim Brown and Kevin Hanley (union reported names)
  • •Union trial and membership vote passed 79.4%
  • •Vendor 66 Degrees is current provider (formerly Cloud Bakers)
  • •Work‑performance agreement passed 83%

Decisions

  • •Addendum approved
  • •Board acknowledged union election results
  • •Claims list approved
  • •Contract 117-2026 approved
  • •Contract approved
  • •Minutes approved
  • •Renewals approved
  • •Street‑closure approved for announced dates

Directions

  • •City to appoint two additional members and assemble full commission; commission to draft final language within statutory period
  • •HR and Police to implement payroll/overtime adjustments
  • •HR to present remaining merit language when complete
  • •Staff to issue necessary permits and coordinate owners
5
Nov

Richmond Power & Light Board of Commissioners Budget Meeting of November 4, 2026

Indiana//Richmond City

The Richmond Power & Light Board held a special Nov. 4, 2026 meeting to review the utility's proposed 2027 operating and capital budgets, discuss major capital needs including aging transformers and a potential intertie substation, and hear updates on AMI deployment and Parallax (the utility's fiber/business services division).

Discussion Points

  • •2027 budget includes funding for an additional installer as a contingency.
  • •2027 scheduled wood-pole testing (every 10 years) with replacements to follow for failed poles.
  • •$500,000 will be allocated from meter capital to an LED relamp pilot in 2027.
  • •Budget conservatively for 2027 sales (about 920 million kWh).
  • •Budget includes a 3% COLA consistent with the IBEW contract.
  • •Consider mechanics\u0019 one-ton truck vs. stretching frontline assets; many garage doors and building-control parts are obsolete.
  • •Early-stage intertie-substation planning with EMPA/AEP could provide needed redundancy ahead of Whitewater Valley Station closure in 2034.
  • •Monitor revenues after the 2026 rate adjustment before beginning most capital projects.
  • •Parallax reported revenue growth and is largely self-funding.
  • •Pilot will cover main corridors first and include labor to assess scalable costs.
  • •Replace end-of-life AEDs and a 30-year garage sweeper.
  • •Two 69 kV transformers (manufactured 1974) need replacement and are multi-year procurements.
  • •Use GASB accounting rules (GASB 68, GASB 101) in financial reporting.
  • •Utility lost significant experience to retirement; training lines are increasing to address skill gaps.

Directions

  • •Board to monitor Parallax revenue and approve hire only if justified by demand.
  • •Staff to consider centralizing some training budgets and continue succession planning (training hires to overlap with retirees).
  • •Staff to continue engineering studies, investigate regulatory transmission-operator implications and return with cost/timing for board approval.
  • •Staff to continue monitoring kWh sales and revenue receipts and report back before authorizing capital starts.
  • •Staff to prioritize capital purchases and schedule pole testing; report timing and bids at follow-up meeting.
  • •Staff to run the pilot and report back with progress and cost-per-mile estimates.
29
Oct

Richmond Board of Public Works Meeting 10/29/2026

Indiana//Richmond City

The Richmond Board of Works and Safety approved routine financial claims and a series of permits and event street closures, awarded a demolition contract, accepted surplus equipment from Wayne County, and authorized sale of two vacant Irish Hill lots; several staff members presented the requests and motions carried on each item.

Discussion Points

  • •Chair ran through items and called for motions; no substantive debate recorded.
  • •Chair referenced a letter listing the equipment Wayne County was offering.
  • •Date correction from Oct. 26 to Oct. 31 noted; Stevens acknowledged the error.
  • •Hayes explained history of city ownership, utility easements limiting development, encroachment issues, and an adjacent owner's expressed interest.
  • •No further details were provided during the meeting.
  • •Ritchie presented bid award and requested contract approval.
  • •Stevens acknowledged one event request arrived late due to internal communication.
  • •Stevens confirmed route details and that police would manually handle intersections on US 27.
  • •Stevens explained the need for and duration of the closure; board accepted the report.
  • •Stevens reported visual inspection and ordinance compliance.

Decisions

  • •Alley closure approved for Oct. 31.
  • •Board approved the three sign renewals.
  • •Closure ratified.
  • •Closures approved.
  • •Contract approved as presented.
  • •Financial claims and payroll items approved as presented.
  • •Resolution approved authorizing acceptance.
  • •Resolution approved to sell two parcels as described.

Directions

  • •Planning department to publish legal ad and notify abutting landowners; accept bids by Dec. 4.
  • •Street department to place barricades per submitted route maps.
21
Oct

Richmond Redevelopment Commission Meeting 10/20/2026

Indiana//Richmond City

The Richmond Redevelopment Commission on 2026-10-20 approved minutes and several funding actions, de‑obligated funds from a prior hospital set‑aside, heard presentations and approved resolutions for Project Phoenix TIF and bond pledge, awarded roadway and Star District/ Reed Center appropriations (the Reed Center award was amended to split $500,000 across 2026–27).

Discussion Points

  • •Anne described acquisition, phased priorities (life/safety, climate control) and fundraising status; Kevin explained state variances that lowered estimated life‑safety costs.
  • •Baker Tilly explained Schedule 2 (TIF estimate), Schedule 3 (sources & uses) and coverage sizing; timing of bond issuance affects capitalized interest and final principal.
  • •Beth explained TIF estimate revisions and vendor credits increasing available funds to approximately $2,000,001.26 across allocation areas.
  • •Beth listed eligible segments and explained the 50% state match and corrected GIS mapping from earlier applications.
  • •Commissioners asked about match amounts and timeline for awards.
  • •Commissioners asked about vandalism and security; Rayantko described interior security and plans to enhance exterior monitoring without harming historic character.
  • •Commissioners asked for clarification on mapping and prior obligations; staff explained projections include assumed commitments to Smith Hill and Richmond Community Schools.
  • •Commissioners asked for recipient lists and project mapping; staff agreed to provide them.
  • •EDC described funding sources including Ready 2.0/Lilly Endowment, local blight funds and private investment; outlined acquisition and asbestos abatement plans.
  • •Staff emphasized the bond will be purchased by the developer and that risk rests with the developer, not the city.

Decisions

  • •Amend and approve Resolution 13‑20‑26 to authorize $250K in 2026 and $250K in 2027 for Reed Center work.
  • •Approve appropriation of up to $485,605.95 for the Community Crossings match.
  • •Approve Resolution 12‑20‑26 to provide funding support for the Star District project.
  • •De‑obligate $1,016,006.81 from ordinance 15‑20‑17; approve current financials and projections.
  • •Pledge of TIF to bond repayment approved (Resolution 10‑20‑26).

Directions

  • •EDC to supply a list of business grant recipients and a property map to commissioners.
  • •Reed Center to proceed with bids and reimbursements accordingly.
  • •Split the award across two fiscal years to align with budget and project phasing; treat the program as a reimbursable grant requiring receipts.
  • •Staff to finalize amortization and sources/uses pending bond closing date.
  • •Staff to monitor award announcements and begin procurement if funding is awarded.
  • •Staff to reflect de‑obligation on the next financial report and show obligations on the next financial statements.
20
Oct

City of Richmond Unsafe Building Committee Meeting 10/20/2026

Indiana//Richmond City

Emergency vacates at two properties were affirmed by the Unsafe Building Commission after inspectors reported electrical hazards and blight-related safety concerns.

Discussion Points

  • •Illegal tap bypassing meter created fire hazard; inspectors disconnected utility and requested RP and L assistance.
  • •Inspector photos show corroded lug, undersized/outdoor misuse of indoor-rated cable, and a panel compromised by weather exposure.
  • •Inspector posted 'unfit' placards and law-department vacate letter on 09/24; property owner listed as Don Ballinger (owner since 2003).
  • •No public speakers addressed either item during the public hearings.
  • •Police assisted in removing occupant belongings under inspector direction; asbestos contractor was on site and demolition contractor B and B Construction was engaged.
  • •Two emergency enforcement items reviewed and affirmed following inspector reports.

Decisions

  • •Affirmation of enforcement authority's emergency action for the property; no additional board orders recorded.
  • •Affirmation of the enforcement authority's emergency action for 517 North 20th.
  • •Both emergency actions affirmed by vote.

Directions

  • •Attach all inspector photos, abatement and demolition documentation to enforcement files and minutes.
  • •Attach photographic evidence and enforcement recommendation to the case file; no further board-directed remedies recorded at the meeting.
  • •Collect abatement and demolition documentation for enforcement file; confirm removal was completed and that occupants were removed from the premises after the posted time.
19
Oct

Richmond Common Council meeting 10/19/2026

Indiana//Richmond City

Richmond Common Council met Oct. 19, 2026. Council voted to hold Ordinance 42 and refer it to a Committee of the Whole, approved a special appropriation resolution amending the 2026 budget, and passed several ordinances including a statutory compliance fund, a food-and-beverage park rainy-day fund, the 2027 salary ordinance and a 2027 budget appropriation. The mayor showed a short video and council scheduled a Committee of the Whole for Nov. 2.

Discussion Points

  • •Controller offered to answer questions
  • •Finance committee positive recommendation for special appropriation
  • •Finance committee recommendation for budget appropriation
  • •Finance committee recommendation for salary ordinance
  • •Finance committee recommended establishing the rainy-day fund
  • •Mayor introduced AIM Summit video highlighting municipal services
  • •Motion to hold Ordinance 42 and refer to Committee of the Whole
  • •No public speakers for/against
  • •Ordinance required for statutory compliance
  • •Scheduling Committee of the Whole for Nov. 2 at 6 p.m.
  • •Staff acknowledgement and plan to review overtime budgeting
  • •Typo in fund number on agenda
  • •Warning about structural underfunding of some line items

Decisions

  • •Ordinance 41-20-26 adopted
  • •Ordinance 42 held and referred to Committee of the Whole
  • •Ordinance 43-20-26 adopted (7–1)
  • •Ordinance 45-20-26 adopted
  • •Ordinance 57-20-26 adopted; follow-up analysis requested
  • •Resolution 25-20-26 approved by roll call

Directions

  • •Clerk to correct published fund number
  • •Clerk to publish Committee of the Whole meeting notice
  • •Staff to evaluate overtime budgeting and review underfunded accounts
15
Oct

Richmond Board of Public Works Meeting of October 15, 2026

Indiana//Richmond City

The Richmond Board of Works and Safety on Oct. 15 approved minutes and payroll claims, continued a road closure for safety at Sim Hodge and Parkway, and approved multiple city contracts including demolition, roadway repairs, a training facility gate, and a Lexapol training subscription. All motions carried by voice vote.

Discussion Points

  • •Baker described limitations of the existing 3-foot pass gate for hose deployment.
  • •Board asked whether content is in-person versus video and about presentation format.
  • •Board members had no further questions and approved the contract.
  • •Board members inspected the site and supported rapid contracting.
  • •Board moved and approved the contract by voice vote.
  • •Chair and members asked about reopening timeframe.
  • •Handicap sign requests were inspected and found to meet the city ordinance.
  • •Keller presented the bid amount and requested approval.
  • •Lips explained the training is video-based, supervisor-led, and keeps officers current on case law and tactics.
  • •Most items were routine approvals and contracts; Parkway Lane repair was expedited due to flood washout.
  • •Need to continue closure due to worker safety and vehicles breaching barricades.
  • •Staff cited a major washout during the flood as the reason to expedite repairs.
  • •Stevens estimated reopening in December, pending completion of work.

Decisions

  • •All listed motions carried by voice vote.
  • •Board approved continuation of the closure by voice vote.
  • •Contract 1232026 approved.
  • •Contract 1262026 approved by voice vote.
  • •Contract 1272026 approved.
  • •Contract approved.

Directions

  • •Department to implement modules during shift briefings after contract execution.
  • •Department to schedule installation with the contractor.
  • •Staff to execute contract and coordinate demolition permitting.
  • •Staff to execute contracts and inform board when actions complete.
  • •Staff to notify board when work is complete and reopening is feasible.
  • •Staff to proceed with contract execution and scheduling.
15
Oct

City of Richmond Board of Zoning Appeals Meeting 10/14/2026

Indiana//Richmond City

Board of Zoning Appeals considered AP Development's "Legacy On Main" redevelopment—100 apartments and ~30,000 sq ft retail—heard public comment on first-floor dwelling units, and approved a series of special-exception and variance petitions allowing first-floor units and reduced unit-size minimums.

Discussion Points

  • •Board debated contingency language and struck a written-commitment clause that would have tied these approvals to other petitions.
  • •Board questioned definitions (studio vs efficiency) and whether minimum sleeping-area rules would be met.
  • •Developer argued studios have full kitchens and quality finishes and that small units enable affordability and feasibility of historic rehab.
  • •Developer described funding sources: Lilly Endowment, Earlham College/partnership grants, federal historic tax credits, local project TIF, private debt.
  • •Developer described on-site management and parking arrangements (own lot ~27 spaces and agreement for 80 garage spaces).
  • •Developer explained that 24 first-floor units would mostly be on rear/side areas; Jenkins building footprint constrains some units to <700 sq ft.
  • •Developer presented scope: 100 apartments, ~30,000 sq ft retail, historic preservation approach.
  • •Members asked staff for clarity on the relation to the comprehensive plan and special-exception standards.
  • •Opponents argued first-floor residential would reduce street-level retail and walkability.
  • •Opponents raised parking concerns given other downtown projects and questioned market demand for small apartments at higher rents.
  • •Staff recommended approval, citing compatibility with plan goals and no health/safety objections.
  • •Supporters said retaining retail frontage plus adding residents will improve downtown vitality.

Decisions

  • •Approved BZA 21–24 individually based on staff findings
  • •Approved BZA 25–30 variances enabling unit sizes below 700 sq ft in constrained historic buildings
7
Oct

City of Richmond Sanitary District Board of Commissioners 10/06/2026

Indiana//Richmond City

The Richmond Sanitary District and its Stormwater Management Board met on 2026-10-06 to approve minutes and invoices, adopt 2027 budgets for both boards (resolutions 005-2026 and 002-2026), approve vendor contracts and permits, and approve a change order for the wastewater treatment plant levee project.

Discussion Points

  • •1,000-series account changes mirror sanitary board; revenue includes possible Midwest Industrial Park rate increase.
  • •Baker Tilly review of civilian positions may change 1,000-series account totals; USGS agreement added ~$4,000 to a 3,000-series account.
  • •Budget remains balanced whether the rate increase is implemented; bond payments are budgeted where applicable.
  • •Change order net reduced original contract by $19,948.79; levee protected the treatment plant during recent flooding.
  • •FEMA offered full mitigation coverage for eligible improvements (e.g., raising transformer, sealing building).
  • •Long-term option to relocate MRF to landfill estimated $3–5 million; removing building from floodplain could cost $2–4 million.
  • •Recommendation to approve two permits for Custom Fit Plumbing LLC with specified permit numbers and expiration date.
  • •Testing will assess pipe condition to determine need for replacement before design completion.
  • •The referenced revenue account does not pay any bonds; the existing rate is roughly 16–17 years old.
  • •Three bids opened and amounts recorded; all acknowledged addendum #1.

Decisions

  • •Adopt 2027 budget via resolution 005-2026.
  • •Adopt 2027 stormwater budget via resolution 002-2026.
  • •Approve change order to contract 136-2025.
  • •Enter agreement with Acuron for ultrasonic thickness testing.
  • •Recommend approval of permits R-CFP-20262728 and R-CFP-20262729.
  • •Refer bids to management.

Directions

  • •Director to share finalized rate report and bond amortization details with board.
  • •Management to evaluate bids and return recommendation.
  • •Proceed with agreement and testing; report results to board.
  • •Staff to complete permit issuance paperwork.
  • •Staff to monitor Midwest Industrial Park rate action and report changes to forecast if council acts.
  • •Staff to prepare FEMA mitigation documentation and to continue planning for potential MRF relocation using capital improvement funds.
2
Oct

City of Richmond Parks Board Meeting 10/08/2026

Indiana//Richmond City

The Richmond Parks and Recreation Board met in October to review routine administration reports, approve two contract addenda (a design expansion and revised pole-barn gates), discuss infrastructure projects (roofs, playground, pump house), review grant opportunities from the Lilly Endowment, and hear updates on markets, community programs and FEMA flood documentation.

Discussion Points

  • •Eligibility for Lilly Endowment planning grant and application deadline (Oct. 30).
  • •Market revenue and vendor-fee totals; SNAP/WIC redemption amounts; farm-to-pantry serving totals.
  • •New trash-cans expected to reduce attractants; community asked to help keep trash off the ground.
  • •Overview of competitive implementation phase and potential award amounts.
  • •Playground installation percentage complete and security-camera upgrade details.
  • •Reason for correction (original incorrect $6,500 figure).
  • •Scope increased to 1,200 sq ft and additional $4,200 cost.
  • •Status of pump house pump, irrigation planning for greens and fairways, EG Hill fountain restoration progress.
  • •Two gates to be added to pole barn and correct cost is $13,000.
  • •Vulture presence at Glenmuller Park and linkage to exposed trash.

Decisions

  • •Addendum approved
  • •Revised addendum approved

Directions

  • •If application is submitted, staff will bring the proposal to the board for review after submission.
  • •Install new trash cans and monitor results.
  • •Staff to work with consultants to prepare the planning grant proposal by Oct. 30.
2
Oct

Richmond Board of Public Works Meeting 10/08/2026

Indiana//Richmond City

Richmond Board of Works approved routine minutes, multiple payment and payroll items, several city contracts and bid awards, granted street closures for a local fundraiser and an emergency railroad crossing repair, and adopted procedures for a new Richmond Fire Merit Commission.

Discussion Points

  • •Board reviewed and approved multiple payment batches and payrolls.
  • •Event logistics, route, participant sign-up, and safety staffing were explained by presenters.
  • •Low bid selection and recommendation from Code Enforcement.
  • •Reimbursement arrangement with high school, previous year's cost (~$42,000), and RCS review status.
  • •The resolution outlines voting protocol, notices, proxy procedures and tie-breaking methods.
  • •Timing of closure (7 a.m. Oct. 12–5 p.m. Oct. 15) and signage to preserve business access.
  • •Whether equipment is new or replacement (Clark said new for incoming apparatus) and timing to secure a 10% discount.

Decisions

  • •Approve contract for extrication tools.
  • •Approved both contracts and authorized signature.
  • •Approved emergency closure.
  • •Approved listed payments and payrolls.
  • •Approved street closure for fundraiser.
  • •Award contract to low bidder.
  • •Resolution adopted.

Directions

  • •Authorize president to sign lease agreement after approval.
  • •City to contact Norfolk Southern about closure policy and coordinate signage.
  • •Staff to implement notices and schedule elections per the resolution.
  • •Street department to pick up barricades after event.
2
Oct

Richmond Advisory Plat Committee 10/07/2026

Indiana//Richmond City

Richmond City Plat Committee met Oct. 7, 2026, and approved two minor subdivision plats: SP5-2026 (split for a proposed Dutch Brothers at 2110 Chester Boulevard) and SP7-2026 (split at Kroger Plaza, 3707/3703 East National Road). Staff recommended approval for both as consistent with the Richmond 2025 comprehensive plan.

Discussion Points

  • •Agent described new building configuration and drive-through placement; NDOT denied a new arterial opening so access will use existing drives and a new easement.
  • •Agent presented that architectural plans were submitted to the state; stormwater measures exist on site; access coordination with INDOT handled by Meyer Development and A and F Engineering.
  • •Staff confirmed comp plan and UDO compliance and noted landscape/dumpster plans received.
  • •Three formal approvals recorded (minutes, SP5, SP7); SB8 removed from agenda.

Decisions

  • •Approvals carried; no further business; meeting adjourned.
  • •Committee approved SP5-2026 as presented.
  • •Committee approved SP7-2026 as presented.

Directions

  • •Developer to finalize easement language and coordinate design with NDOT and city staff.
  • •Planning staff to issue addresses and track follow-ups for easement/NDOT coordination.
  • •Staff to issue address on request and to continue coordination on INDOT access issues with developer representatives.
1
Oct

Richmond Common Council & RP&L Board of Directors 10/05/2026

Indiana//Richmond City

Richmond Common Council met Oct. 5, 2026. The council approved the annexation of a 7.34-acre parcel for a convenience store, advanced multiple budget and salary ordinances to second reading (including a 2027 budget public hearing), rejected an ordinance on unauthorized relocation of transient individuals, and debated a proposed fire-department capital fund before referring it to finance. Richmond Power & Light discussed a coal ash remediation project and approved a vehicle purchase.

Discussion Points

  • •Council expressed support and appreciation for officers.
  • •Council had no public opposition and asked no substantive follow-up questions.
  • •Councilors asked for further breakouts of funds dipping into cash reserves.
  • •Council requested documentation to demonstrate existing fund flows and transparent accounting.
  • •Indiana submitted CCR permit program to EPA; EPA review may affect schedule.
  • •Payroll line-item corrections noted; Fields confirmed figures and committee referral history.
  • •Planning staff presented fiscal plan and infrastructure commitments; Advisory Plan Commission recommended 9–0.
  • •Public commenter supported having an ordinance to address visible homelessness concentrations.
  • •Public Safety committee and police chief raised enforcement and legal concerns.
  • •Purcell argued ordinance duplicates existing fund and could obscure accounting; staff cited GFOA best practices.
  • •Recorded approvals, referrals and defeats summarized for transparency.
  • •Staff presented general fund estimate and fund‑level balances; Fields cited expected revenue losses from circuit breakers and Senate Enrolled Act 1.
  • •Staff summarized permitting history, bond planning and project cost estimate (just shy of $30M).

Decisions

  • •Council adopted Resolution 20-20-26 and approved ordinance 32-20-26 (annexation) by roll-call/voice vote.
  • •Listed votes and next steps.
  • •No adoption tonight; public hearing closed.
  • •Ordinance 42 referred to finance committee; no final adoption tonight.
  • •Ordinance 50 failed on roll-call; no code change enacted.
  • •Ordinance 54 advanced and approved by roll-call.
  • •Vehicle purchase approved; CCR update informational only.

Directions

  • •Continue committee work on comprehensive responses addressing homelessness.
  • •Planning staff to coordinate next steps for utility extensions and signal installation agreements.
  • •Proceed with administrative steps to implement compensation in payroll and budget.
  • •Refer Ordinance 42 to the finance committee for additional analysis.
  • •RP&L staff to track IDEM/EPA actions and report schedule/bonding implications to board.
  • •Staff and committees to report back on referred items prior to Oct. 19 where applicable.
  • •Staff to provide additional fund‑level documentation ahead of Oct. 19 adoption meeting.
24
Sep

Richmond Board of Public Works Meeting of September 24, 2026

Indiana//Richmond City

The Richmond Board of Works and Safety met Sept. 24, 2026, approving routine minutes and claims, renewing one handicap parking sign, approving street closures for the Fourth Street Fair (Oct. 2–4), taking demolition bids for 400 S. 12th St. under advisement, approving a vehicle purchase contract, adopting a Roseview Transit drug-and-alcohol policy update (Resolution 8-2026), and approving the 2027 holiday schedule before adjourning.

Discussion Points

  • •Claim batch 92526 read as $281,366.76.
  • •Finance explained the Christmas observation shift because the holiday falls on a weekend.
  • •INDOT requested policy update; staff reviewed 27-page template and noted a single minor change.
  • •Officer Stevens stated sign meets city ordinance specifications.
  • •Presenter explained the request was routed to another department earlier; dates and barricade locations were noted.
  • •Three bids read: Mike's Escavating $33,750; Cox Escavating $33,500; BNB Construction $22,500.
  • •Wetzel Ford previously awarded contract on Aug. 27, 2026; not-to-exceed amount $147,927.

Decisions

  • •Claims approved by voice vote
  • •Contract approved for purchase authorization
  • •Holiday schedule approved
  • •Proof of publication accepted; public hearing opened and closed with no speakers
  • •Renewal approved
  • •Resolution approved to adopt updated policy
  • •Street closures approved as requested

Directions

  • •Refer bids to purchasing for evaluation.
22
Sep

Richmond Common Council Committee of the Whole of September 22, 2026 (Complete Meeting Recording)

Indiana//Richmond City

Richmond City committee of the whole reviewed the proposed 2027 budget, department-by-department presentations, a reorganization to comply with House Enrolled Act 1001, and several contested procedural questions about transfers, vendor payment timing and a new front-desk hire. Council set deadlines for the public notice and adopted several placeholders for capital and operating funds.

Discussion Points

  • •Council asked for a grant framework and agreed to a placeholder rainy‑day fund.
  • •Council members expressed concern about small-business vendors being forced to carry invoices longer.
  • •Council should expect additional appropriation requests if overtime gaps persist.
  • •Council voted to fund two part‑time positions to staff the city building entrance; police will vet candidates.
  • •Department will apply for the Lily Endowment $150,000 planning grant to become eligible for a larger capital award.
  • •Diesel and equipment costs create budget risk for fire operations.
  • •EMS projects a significant overtime shortfall and proposes civilian medics to reduce overtime.
  • •HEA 1001 requires a separate fund for building permit revenue and inspections.
  • •Mayor framed 2027 budget around infrastructure, development and department reorganizations.
  • •Parks seeks redesign and maintenance funding for downtown bike path and other assets.
  • •Personnel and revenue lines will move into a new division and fund; interfund transfer will seed initial operations.
  • •Police are down seven officers and face a long hiring timeline; training and promotional processes will continue.
  • •Requiring transfers to go to full council increases oversight but extends invoice-to-payment time.
  • •Staff emphasized notice deadlines for Gateway upload and public hearing (Oct. 5) and adoption (Oct. 19).
  • •Targeted enforcement results (110 lbs of narcotics, 17 firearms) reflect active investigations.

Decisions

  • •Council accepted plans and expects follow‑up on overtime and apparatus funding.
  • •Council accepted the reorganization concept and asked for details to implement fund 2514.
  • •Council approved a $150,000 placeholder and asked staff to pursue the Lilly planning grant and present a grant framework.
  • •Council approved publishing preparations; public hearing set for Oct. 5.
  • •Motion to fund two part‑time information‑desk positions passed.
  • •Motion to require full-council approval for transfers failed; no ordinance change adopted.

Directions

  • •Administration to add a placeholder for two part‑time info-desk positions in the general fund and prepare job descriptions and vetting procedures with police.
  • •Council must submit final changes by Friday to meet the Gateway publication deadline.
  • •EMS leadership to return with specific appropriation requests and implementation plan for civilian‑medic pilot once union ratification progresses.
  • •Staff to prepare alternative transfer approval models that reduce council workload but preserve oversight and minimize vendor-payment delays.
  • •Staff to provide full expenditure detail for fund 2514 and the proposed intergovernmental transfer.
  • •Staff to return with RFP responses for bike path redesign and a proposal for the food & beverage grant program and rainy‑day reserve.
22
Sep

Richmond Common Council Committee of the Whole of September 22, 2026 (Livestream Recording)

Indiana//Richmond City

Richmond City council held a lengthy budget review covering department budgets, proposed fund transfers, new organizational changes (including a separate building-safety fund), public-safety staffing and overtime concerns, downtown parking enforcement and a food & beverage pay-as-you-go plan. Council approved a funded front-desk position (two part-time posts) and directed follow-ups on several budget line items.

Discussion Points

  • •Budget includes an intergovernmental transfer to fund the new division in 2027.
  • •Council also discussed downtown parking enforcement and technology options such as automated gates or license-plate scanning.
  • •Council and administration proposed creating a non-reverting apparatus reserve funded at $250,000/year.
  • •Council debated whether the front-desk role should be full-time or several part-time positions funded by the general fund.
  • •Council weighed trade-offs between internal controller authority (speed) and full-council approval (oversight).
  • •EMS projected a large overtime shortfall and proposed three civilian medics to reduce overtime.
  • •Fire chief noted diesel fuel price risk and budget sensitivity.
  • •House Enrolled Act 1001 requires separate accounting for building permit/inspection revenue and fines.
  • •Mayor's office handles estimated 11,000 phone calls and 23,500 emails annually.
  • •Minor increases in mayoral fuel for legislative travel.
  • •Motion to permit transfers failed for lack of second.
  • •Parks achieved volunteer and participation gains while absorbing a $350,000 cut.
  • •Personnel moved from mayor's office to other departments; one position eliminated.
  • •Police presented 15,000 calls in the first half of 2026 and targeted-enforcement seizures (110 lbs narcotics, 17 firearms).
  • •Proposed uses for food-and-beverage receipts include a rainy-day reserve, equipment replacement, maintenance contracts and a community-event grant program.
  • •Staff proposed moving building inspectors and the building commissioner into new Division of Building Safety and Community Standards funded by 2514.
  • •Staff repeated that funds appropriated for a category must be used for that category and cited 364-6-21 as the oversight mechanism.
  • •Staff want to pursue a $150,000 Lily Endowment planning grant to qualify for larger capital funds.

Decisions

  • •Council supported creating an apparatus reserve in principle; staff to formalize fund and ordinance.
  • •Create and fund two part-time front-desk positions; form a parking committee.
  • •No appropriation for new projects approved without further RFP/bid information.
  • •No change enacted at meeting; motion failed.
  • •No formal action taken; presentation accepted.
  • •Structure proposed; council will review details in follow-up materials.

Directions

  • •Add two part-time information-desk positions to the general fund budget as a placeholder and prepare job descriptions.
  • •Administration to draft ordinance creating cumulative capital fund for apparatus replacement and specify permissible uses.
  • •Administration to provide a detailed expenditure list and updated org chart for council review prior to adoption.
  • •Administration to return with RFP responses, cost estimates for bike-path redesign and ordinance language for a rainy-day reserve before final appropriation.
  • •Council to review departmental flowcharts and departmental budgets later in the meeting.
  • •EMS to return to council if overtime shortfalls require supplemental appropriations.
  • •Form a parking committee to explore enforcement, attendant models, permit structures and technology for downtown lots and the parking garage.
  • •If legal opinion permits, prepare ordinance or administrative procedure for council consideration.
  • •Staff to obtain legal opinion from counsel and state board of accounts contact on internal transfer authority.
22
Sep

City of Richmond Sanitary District Board of Commissioners of Tuesday, September 22, 2026

Indiana//Richmond City

At its Sept. 22, 2026 meeting, the Richmond Sanitary District Board approved minutes and invoices totaling $405,435.11, received a directors report announcing leaf collection starting Oct. 26 and installation of recycling equipment, and scheduled a public hearing on the budget for Oct. 6.

Discussion Points

  • •Director noted minor salary-line changes and corrections to capital improvement fund formulas in budget materials.
  • •Installation and initial use of grant-funded recycling baler and compactor; planned route and can distribution changes beginning early next year.
  • •Leaf collection start date (Oct. 26) and six-week schedule; sanitary district handles leaves within district boundary while street department covers others.
  • •No substantive discussion or questions recorded during the invoice motion; mover read amounts and notable vendors.

Decisions

  • •Approve invoices totaling $405,435.11
  • •Schedule Oct. 6 public hearing for budget resolutions.

Directions

  • •Director to review and present the corrected items at the Oct. 6 public hearing.
  • •Staff to roll out information and phase in containers; surveys to be used before outreach to neighboring communities.
15
Sep

City of Richmond Unsafe Building Committee Meeting of September 15, 2026

Indiana//Richmond City

The Richmond Unsafe Building Commission on 2026-09-15 affirmed an emergency demolition order for the duplex at 1110 and 1112 South B Street after staff described structural collapse risk and neighbors reported drug activity and safety concerns.

Discussion Points

  • •A commenter linked demolition and blight removal to neighborhood rehabilitation efforts in the Vail District.
  • •Resident described alleged meth production, a weapons standoff and repeated police calls at the property.
  • •Sherry presented photos and asserted structural failure risk; staff reported repeated code violations and re-occupations.
  • •The clerk asked staff how many violations had been issued; staff estimated at least 12 over five to six years.

Decisions

  • •Motion to affirm emergency demolition for 1110 and 1112 South B Street passed by voice vote.
  • •Testimony provided context used by the commission before affirming the emergency demolition action.

Directions

  • •Enforcement authorities' recommended demolition was affirmed by the commission.
10
Sep

City of Richmond Board of Zoning Appeals Meeting of Wednesday, September 9, 2026

Indiana//Richmond City

Richmond City Board of Zoning Appeals approved three variances on Sept. 9, 2026: a detached garage enlargement, legalizing a small private school on agricultural land, and reductions to front-yard setbacks to allow accessory structures; the board also moved the November meeting to Nov. 17.

Discussion Points

  • •Agent explained need to partition parcel to support pole barn; staff and one public respondent supported proposal; gravel parking not part of variance.
  • •Board discussed Veterans Day conflict and individual scheduling preferences.
  • •Petitioner described enrollment ("low twenties"); neighbors expressed support; staff described zoning conflict and recommended approval.
  • •Petitioner requested larger garage due to small primary-structure footprint; planning staff and utilities consulted; no public opposition in hearing.

Decisions

  • •November meeting moved to Nov. 17, 2026.
  • •Variance approved to allow school use on agricultural parcel, with written commitment.
  • •Variance approved with two written commitments.
  • •Variance approved; written commitment that no future accessory structures will be permitted.

Directions

  • •Petitioner to combine lots via minor subdivision and submit permit plans to infrastructure development office.
  • •Petitioner to obtain building permits and coordinate electrical work with Richmond Power & Light and building inspection.
  • •Petitioner to secure Wayne County permits and inspections; building commissioner to perform final checks.
  • •Staff to post the updated meeting date.
Ronald (Ron) Oler, Ph.D.
Mayor
Anne Taylor
Council - District No. 5 — District No. 5
Bill Engle
Council - District No. 3 — District No. 3